2-MPL(IGN)-CM-'38
NATIONAL RAILROAD ADJUSTMENT BOARD
SECOND DIVISION
PARTIES TO DISPUTE:
SYSTEM FEDERATION No. 14, RAILWAY EMPLOYES'
DEPARTMENT, A. F. of L. (Carmen)
MISSOURI PACIFIC LINES
(International-Great Northern Railroad Company)
DISPUTE: CLAIM OF EMPLOYES: That the removal and application
of top center plates and top side bearings is the work of journeymen car
builders and not freight car truckmen.
STATEMENT: The above question was submitted to the Second Division
of the National Railroad Adjustment Board by the above referred to organization in ex parte form, and the Division is now in receipt of request from
the employes that the case be withdrawn.
AWARD
Claim dismissed.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Second Division
ATTEST: J. L. Mindling
Secretary
Dated at Chicago, Illinois, this 21st day of September, 1938.
[413]