PARTIES TO DISPUTE:

SYSTEM FEDERATION NO. 10, RAILWAY EMPLOYES'

DEPARTMENT, A. F. OF L. (MACHINISTS)


THE DENVER AND RIO GRANDE WESTERN RAILROAD
COMPANY ,

DISPUTE: CLAIM OF EMPLOYES: That the setting up, reading blue prints and drilling locomotive cylinders at Denver, Colorado, is the work of a machinist and not that of a helper in accordance with Rule 46 of agreement dated September 1, 1940.


STATEMENT: The above question was submitted to the Second Division of the National Railroad Adjustment Board by the above referred to organization in ex parte form, a hearing thereon was held, and the Division is now in receipt of request from the employes that the case be withdrawn.




Case dismissed.

            NATIONAL RAILROAD ADJUSTMENT BOARD

            . By Order of Second Division


ATTEST: J. L. Mindling
Secretary

Dated at Chicago, Illinois, this 9th day of September, 1942.

                  [97]