Award No. 1052
Docket No. 1001
2-N&W-MA-'45
NATIONAL RAILROAD ADJUSTMENT BOARD
SECOND DIVISION
PARTIES TO DISPUTE:
SYSTEM FEDERATION NO. 16, RAILWAY EMPLOYES'
DEPARTMENT, A. F. OF L. (MACHINISTS)
NORFOLK AND WESTERN RAILWAY COMPANY
DISPUTE: CLAIM OF EMPLOYES:
(1) That under the controlling agreement and particularly Rule 54,
the removal, inspection, adjusting, repairing and installing Lubricators is machinists' work.
(2) That the carrier is violating the controlling agreement and particularly Rule 31, when machinists' helpers are assigned to perform the aforesaid work.
(3) That the carrier be ordered to discontinue the assignment of machinists' helpers to perform the lubricator work herein referred to.
STATEMENT: The above question was submitted to the Second Division
of the National Railroad Adjustment Board by the above referred to organization in ex parte form, a hearing thereon was held, and the Division is now
in receipt of request from the employes that the case be withdrawn.
AWARD
Claim dismissed.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Second Division
ATTEST: J. L. Mindling
Secretary
Dated at Chicago, Illinois, this 1st day of February, 1945.