SYSTEM FEDERATION NO. 30, RAILWAY EMPLOYES'
DEPARTMENT, A. F. OF L. (Sheet Metal Workers)
DISPUTE: CLAIM OF EMPLOYES: That under the current agreement Sheet Metal Worker H. B. Geyer was unjustly deprived of his service rights when furloughed from March 16 to April 1, 1949, and that accordingly the carrier be ordered to reimburse this employe for all of said time lost.
STATEMENT: The above question was submitted to the Second Division of the National Railroad Adjustment Board by the above parties jointly, and the Division is now in receipt of request from them that the case be withdrawn.