PARTIES TO DISPUTE:

SYSTEM FEDERATION NO. 32, RAILWAY EMPLOYES'

DEPARTMENT, A. F. of L. (Machinists)


CHICAGO, INDIANAPOLIS AND LOUISVILLE

RAILWAY COMPANY


DISPUTE: CLAIM OF EMPLOYES: 1-That under the current agreement it was improper to assign employes of the Vapor Car Heating Company, Inc., to perform machinists' work in the amount of 11A hours on Diesel Engine No. 84 between 12 Noon and 2:30 P. M. on Novmber 29, 1947.


2-That accordingly the carrier be ordered to additionally compensate Machinist C. J. Murphy in the amount of b hours call pay for this work on the date aforesaid.


STATEMENT: The above question was submitted to the Second Division of the National Railroad Adjustment Board by the above referred to organization in ex parte form, a hearing thereon was held, and the Division is now in receipt of request from the parties that the case be withdrawn.







ATTEST: J. L. Mindling
Secretary

Dated at Chicago, Illinois, this 7th day of December, 1949.