PARTIES TO DISPUTE:

SYSTEM FEDERATION NO. 76, RAILWAY EMPLOYES'

DEPARTMENT, A. F. of L. (Carmen)


CHICAGO, MILWAUKEE, ST. PAUL AND PACIFIC RAILROAD

COMPANY


DISPUTE: CLAIM OF EMPLOYES: "That in accordance with the applicable agreements the Carrier be ordered to compensate J. Entwistle, retired Carman, five (5) additional days' vacation pay."


STATEMENT: The above question was submitted to the Second Division of the National Railroad Adjustment Board by the above referred to Organization in ex parte form, hearing thereon was not held, and the Division is now in receipt of a request from the employes that the case be withdrawn.




    Claim dismissed.


                NATIONAL RAILROAD ADJUSTMENT BOARD By Order of Second Division


ATTEST: Harry J. Sassaman
        Executive Secretary


Dated at Chicago, Illinois, this 23rd day of January, 1956.

[2817