Award No. 2217
Docket No. 2347
2-MP-BM-'56
NATIONAL RAILROAD ADJUSTMENT BOARD
SECOND DIVISION
PARTIES TO DISPUTE:
SYSTEM FEDERATION NO. 2, RAILWAY EMPLOYES'
DEPARTMENT, A. F. of L.-C. I. O. (Boilermakers)
MISSOURI PACIFIC RAILROAD COMPANY
DISPUTE:
CLAIM OF EMPLOYES:
1. That under the current agreement other than a Boilermaker
Helper was improperly used to help a Boilermaker on May 5, 6, 9,
10, 11, 12, 13, 16, 17, 18, 19 and 20, 1955.
2. That accordingly the Carrier be ordered to compensate furloughed Boiler Maker Helper Ed Hillman at the applicable rate of
pay for the aforesaid dates.
STATEMENT OF CLAIM:
The above question was submitted to the
Second Division of the National Railroad Adjustment Board by the above
referred to organization in ex parte form, and the Division is now in receipt
of a request from the employes that the case be withdrawn.
AWARD
Claim dismissed.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of SECOND DIVISION
ATTEST: Harry J. Sassaman
Executive Secretary
Dated at Chicago, Illinois, this 6th day of August, 1956.