Award No. 2263
Docket No. 2393
2-T&P-CM-'56
NATIONAL RAILROAD ADJUSTMENT BOARD
SECOND DIVISION
PARTIES TO DISPUTE:
SYSTEM FEDERATION NO. 121, RAILWAY EMPLOYES'
DEPARTMENT, A. F. of L.-C. I. O. (Carmen)
TEXAS AND PACIFIC RAILWAY COMPANY, THE
DISPUTE:
CLAIM OF EMPLOYES:
1. That under the current agreement other than Carmen were
improperly used to make repairs on Texas and Pacific Car No. 6039,
consisting of removing and applying hose on March 24, 1955.
2. That accordingly the Carrier be ordered to additionally
compensate Carman T. C. Eubanks, in the amount of a four (4)
hour call at the applicable rate of pay.
STATEMENT: The above question was submitted to the Second Division of the National Railroad Adjustment Board by the above referred to
organization in ex parte form, and the Division is now in receipt of a request
from the employes that the case be withdrawn.
AWARD
Claim dismissed.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of SECOND DIVISION
ATTEST: Harry J. Sassaman
Executive Secretary
Dated at Chicago, Illinois, this 8th day of October, 1956.