PARTIES TO DISPUTE:

SYSTEM FEDERATION NO. 101, RAILWAY EMPLOYES'

DEPARTMENT, A. F. of L. (Machinists)




DISPUTE: CLAIM OF EMPLOYES: 1. That under the current agreement other than employes of the Machinist Craft were improperly assigned to perform Machinist work in the Power Plant at Havre, Montana, on June 20 and 21, 1955.


2. That accordingly the Carrier be ordered to compensate Machinist Clarence Frey for eight (8) hours at the applicable overtime rate for each day involved.


EMPLOYES' STATEMENT OF FACTS: An induced draft fan was installed at the Havre power plant of the Great Northern Railway Company in 1946. There are two (2) bearings of the water and oil cooled type and are either babbitt or bronze next to the shaft. These bearings are fifteen (15) inches long and the bearing and housing assembled weigh approximately seventy-five (75) pounds. The upper half of the bearing is fitted to a two (2) inch shaft and has an outer jacket for water.


The lower half including the housing is all one piece with an outer jacket for water and an inner reservoir for oil. Both parts save seals fitted to the shaft to retain the oil. To remove these bearings two (2) one and onehalf (11/x) inch nuts must be removed and then the bolts removed from the frame and shaft jacket. These bearing are removed when the unit is shut down for annual inspection and a considerable amount of work is required in examining and fitting the bearings to insure a continuous operation.


This boiler, and induced fan unit, was shut down for several weeks. on June 20 and 21, 1955, during the time the unit was shut down, Chief Engineer Davis and Stationary Fireman O'Leary of the Havre power plant dismantled, repaired and reassembled the bearings on the induced draft fan which consisted of scrapping and fitting.


The agreement effective September 1, 1949 as subsequently amended is controlling. This dispute has been handled with carrier officials up to and including the highest designated official, all of whom have declined to adjust the dispute satisfactorily.



2393-4 :j ,44

However, carrier was willing to transfer this work to machinists in light of power house employes willingness to give it up. However, this claim seeks to enforce the transfer of work prior to the date that the transfer was made.


There can be no question but what the element of jurisdiction is involved in the performance of the work which is the subject of the claim. To bear this out, the facts speak for themselves. For ten years the work was performed by power plant employes at Havre and this work assignment was not protested.


In June, 1955 this same work was again performed by power plant employes. Following the performance and completion of this work on June 20 and 21, 1955, the machinists organization solicited and received an opinion from the general chairman of the organization, whose members performed the work on June 20 and 21, 1955, relative to which craft had the exclusive right to perform such work. It was not until after the organizations reached an understanding on this matter that the present claims were filed.


Through mutual understanding between the organizations involved, and the carrier, relative to this work performed by power plant personnel, it was agreed that this work of removing induction draft fan bearings, cleaning and replacing them, would now become machinists work. This mutual understanding was reached subsequent to June 20 and 21, 1955, upon which dates this work is case was performed for the last time by power plant employes.


In conclusion, carrier firmly contends that this claim of the employes organization is entirely lacking in merit or schedule rule support and must be denied for the following reasons:










FINDINGS: The Second Division of the Adjustment Board, upon the whole record and all the evidence, finds that:



2393-5 445

The carrier or carriers and the employe or employes involved in the dispute are respectively carrier and employe within the meaning of the Railway Labor Act as approved June 21, 1934.


This Division of the Adjustment Board has jurisdiction over the dispute involved herein.




The record indicates that the work in dispute in this docket has been performed by the stationary engineers since the date of the installation of the induced draft fan in 1946 at Havre, Montana, up until date of this dispute in June, 1955.


The record further indicates that the general chairman of the Firemen and Oilers Organization and the general chairman of the Machinists Organization reached an understanding in July, 1955 that work involved in docket was machinists' work. The carrier was advised of this fact in conference on September 14, 1955 and Mr. C. A. Pearson, assistant to president of personnel,. in a letter dated September 16, 1955 confirming the conference, agreed to assign the work involved in this dispute to the machinists in view of the agreement between the two organizations, but objected to paying compensation for time involved in the claim in face of Rule 94 of the controlling agreement. We hold Mr. Pearson's letter assigning this work to the machinists disposes of Part I of the claim. Rule 94 reads













Dated at Chicago, Illinois, this 18th day of January, 1957.