The Second Division consisted of the regular members and in addi

tion Referee Dudley E. Whiting when the award was rendered.


PARTIES TO DISPUTE:

SYSTEM FEDERATION NO. 54, RAILWAY EMPLOYES'

DEPARTMENT, A. F. of L. (Boilermakers)


THE CLEVELAND, CINCINNATI, CHICAGO & ST. LOUIS

RAILWAY COMPANY (The New York Central

Railroad Company, Lessee)








JOINT STATEMENT OF FACTS: Boilermaker L. Hoffman, hereinafter referred to as the Claimant, is employed at the Bellefontaine (Ohio) Engine Terminal and regularly assigned on the 7 A. M. to 3 P. M. shift. Boilermaker L. L. Johns, employed on the 3 P. M. to 11 P. M. shift at this engine terminal had an assigned vacation period of March 15 through March 30, 1954. On March 16, the Claimant was changed from the 7 A. M. to 3 P. M. shift to the 3 P. M. to 11 P. M. shift to fill the job of Boilermaker Johns while he was on vacation, by instructions of the Carrier.


POSITION OF EMPLOYES: It is submitted that under Rule 10 (a) reading




The claimant is entitled to be additionally compensated the difference between the straight time compensation he was paid for services performed on the 3:00 P. M. to 11:00 P. M. shift on March 16, 1954, and the overtime compensation due him under its provisions.



2440-4 707

The claim in the instant case is wholly without merit and should be denied in its entirety.


FINDINGS: The Second Division of the Adjustment Board, upon the whole record and all the evidence, finds that:


The carrier or carriers and the employe or employes involved in this dispute are respectively carrier and employe within the meaning of the Railway Labor Act as approved June 21, 1934.


This Division of the Adjustment Board has jurisdiction over the dispute involved herein.




This claim is for time and one-half under Rule 10, Changing Shifts, where a regularly assigned employe was used to relieve an employe on another shift while the latter was on vacation. Identical claims were sustained by our Awards 1806 and 1807 and were denied by our Awards 2083, 2084, 2197, 2205, 2230 and 2243. Other identical claims are now before us for decision, so the issue will be considered upon a general overall basis.


The first National Vacation Agreement was made on December 17, 1941. Article 14 provided for a joint committee to decide disputes involving the interpretation or application of that agreement, such decisions to be final and binding upon the parties. That committee became deadlocked over a series of questions concerning the meaning and application of that contract and, on July 20, 1942, submitted the same in writing to Wayne L. Morse, as referee, agreeing that his decision upon the issues submitted would be final and binding.


Article 12 (a) of the vacation agreement, so far as pertinent, is as follows:






That presented the identical issue here submitted. The decision of Referee Morse thereon is as follows:




2440-5 708


The Employes contend that Referee Morse, in his interpretations otherwise, recognized that he had no authority to modify existing rules but that his decision upon that issue exceeded his authority. It is obvious that the referee did not believe he was exceeding his authority although he was careful to delimit it. For example, in his interpretation of Article 10, he said (p. 87):


In his interpretation of Article 12 (a) he stated that the carriers contended "that the prohibition as contained in the Vacation Agreement against the use of the vacation system to create unnecessary expense takes precedence over any schedule rule which would create such expense." In connection therewith he said (pp. 98-99)




The pertinent portion of Article 12 (b), referred to in his decision on issue (b), is as follows:

2440-6 709





Careful consideration of the rule involved, the applicable provisions of the vacation agreement and the reasoning of the referee shows that he had no doubt that he was within his authority in making his decision on issue (b) under Article 12. The same considerations make it very doubtful, at least, whether one can reasonably hold that he did thereby exceed his jurisdiction.


Assuming, as has been suggested, that there was some doubt as to the referee's authority to make that decision, let us examine subsequent actions of the parties. Neither of the parties then protested that he exceeded his authority. Quite to the contrary, within a few days after the referee rendered his award, the Railway Employes' Department withdrew from the Second Division, N.R.A.B., an identical claim then pending against the T and N O Railroad.


On February 23, 1945 the parties to the vacation agreement entered into a supplemental agreement, which provided in part as follows:



Later in 1945 a claim arose against the T and N O Railroad which was subsequently processed by the Railway Employes' Department to the Second Division, N.R.A.B. It did not seek pay under the changing shifts rule during a vacation period but, because the employe on vacation remained absent due to illness after his vacation ended, sought pay under that rule for the day after his vacation ended. That claim resulted in our Award No. 1259, wherein we held in part as follows:



It was not until 1953 that this organization processed further claims like this and then for the first time questioned the authority of Referee Morse to decide the issue as he did. Those claims resulted in our Awards 1806 and 1807 on July 12, 1954. Thereafter this Organization and others entered into a national agreement with the Carriers on August 21, 1954. Article I thereof amended the vacation agreement and Section 6 reads in part as follows:




2440-7 710



Thus we find this organization acting in conformity with the particular part of Referee Morse's interpretation, which is now challenged, immediately after it was rendered and on other occasions thereafter; we find it failing to challenge his jurisdiction thereon for at least eleven years; and we find it entering into agreements in 1945 and 1954 specifically providing that his interpretations shall remain in full force and effect. Such a course of conduct effectively estops the Organization from challenging his authority collaterally in these separate proceedings before a different forum. That is the essence of our findings in our Award No. 2197 and our subsequent awards upon the subject, although not expressed in those precise words. Under the circumstances shown no other finding is possible.


In this docket another issue is presented based upon a special agreement governing procedure in appeals to this Board. In view of the foregoing general findings, determination thereof is not necessary in this decision.




    Claim denied.


              NATIONAL RAILROAD ADJUSTMENT BOARD By Order of SECOND DIVISION


              ATTEST: Harry J. Sassaman

              Executive Secretary


Dated at Chicago, Illinois, this 3rd day of June, 1957.

DISSENT OF LABOR MEMBERS TO AWARDS NOS. 2240, 2441,

2442, 2443, 2444, 2445, 2446, 2447, 2448, 2449, 2450, 2451,

2452, 2453, 2454, 2455, 2456, 2457, 2504.


We are constrained to dissent from the majority findings in the aboveenumerated awards for the reasons set forth in our dissents to Awards Nos. 2083, 2084, 2197, 2205, 2230, and 2243.


It is our considered opinion that Awards No. 1514, 1806, and 1807 of the Second Division should have been followed and the overtime rates embodied in the schedule agreements should have been applied.


                      R. W. Blake

                      Charles E. Goodlin

                      T. E. Losey

                      Edward W. Wiesner

                      James B. Zink