Award No. 2452
Docket No. 2171
NATIONAL RAILROAD ADJUSTMENT BOARD
SECOND DIVISION
The Second Division consisted of the regular members and in
addition Referee Dudley E. Whiting when the award was rendered.
PARTIES TO DISPUTE:
SYSTEM FEDERATION NO. 99, RAILWAY EMPLOYES'
DEPARTMENT, A. F. of L. (Carmen)
ILLINOIS CENTRAL RAILROAD COMPANY
DISPUTE: CLAIM OF EMPLOYES:
(1) That under the current agreement the following carmen
were .improperly compensated at the straight time rate for service
performed on the dates as shown opposite their names:
M. M. Newell -July 6, July 20, 1953
Aliby Smith -July 10, July 16, 1953
August 13, August 18, 1953
S. M. Ginn -June 14, June 16, June 18, 1953
July 28, 1953
August 17, August 25, 1953
October 20, 1953
November 3, 1953
(2) That accordingly the carrier be ordered to compensate
the aforesaid carmen additionally in the amount of four (4) hours
pay at the straight time rate for each of the above dates.
EMPLOYES' STATEMENT OF FACTS:
Carmen M. M. Newell, Aliby
Smith, and S. M. Ginn, hereinafter referred to as the claimants, regularly
assigned to work on the repair track from 7 A. M. to 12 Noon, 12:30 P. M. to
3:30 P. M., Monday through Friday with rest days of Saturday and Sunday,
were instructed by the foreman to relieve train yard car inspectors who were
off on their annual earned vacation on the following dates and shifts, and
claimants returned to their regular assigned position on repair tracks as shown
below: Jackson, Miss.
Car Inspector Returned to
Date Shift Relieved Regular Position
Carman Newell
July 6, 1953 3 P. M. to 11 P. M. R. L. Allen July 20, 1953
Carman Smith
July 10, 1953 11 P. M. to 7 A. M. T. E. Shivers July 16, 1953
August 13, 1953 3 P. M. to 11 P. M. W. D. McKay August 18, 1953
[147
2452-13
26
In the findings in Award 1806, the Board, with Referee Carter, said:
"That there is a conflict between the schedule agreement and the vacation
agreement is self evident." Having determined that a conflict existed, the contract ambiguous to the extent of the conflict, the Board should
have proceeded to resolve the conflict in accordance with the recognized
principles for the construction of contracts. Carrier has pointed out in this
submission that one of the accepted principles in the construction of contracts
is that a special provision of a contract, such as the Vacation Agreement in
this case, takes precedence over a general provision, such as the changing
shifts rule. Had that principle been applied, the Board would have reached a
different conclusion in Awards 1806 and 180 7.
The carrier members in their dissent to Awards 1806 and 1807 commented
on the awards' holding that practice will not change an unambiguous rule. The
referee in effect held that the changing shifts rule was plain and unambiguous
and could not be altered by practice. Completely ignored was the fact that
Referee Morse's binding interpretation was likewise completely plain and
unambiguous and, if the Board was to perform properly its duty to interpret
agreements, had to be harmonized with the changing shift rule, which the
Board declared was in conflict with it. The Board failed in Awards 1806
and 1807 to apply a second recognized rule for the construction of contracts,
which is succinctly stated as follows in
12
Am. Jur., Contracts, § 249
:
"Interpretation by Parties.-In the determination of the meaning of an indefinite or ambiguous contract, the interpretation placed
upon the contract by the parties themselves is to be considered by
the court and is entitled to great, if not controlling, influence in
ascertaining their understanding of its terms. In fact the courts
will generally follow such practical interpretation of a doubtful
contract. It is to be assumed that parties to a contract know best
what was meant by its terms and are the least likely to be mistaken
as to its intention; that each party is alert to protect his own interests
and to insist on his rights; and that whatever is done by the parties
during the period of the performance of the contract is done under
its terms as they understoood and intended it should be. Parties are
far less likely to have been mistaken as to the meaning of their
contract during the period when they are in harmony and practical
interpretation reflects that meaning than when subsequent differences have impelled them to resort to law and one of them then seeks
an interpretation at variance with their practical interpretation of its
provisions . . . ."
It is clear that the mutual construction given by the parties to the whole
agreement, including the Vacation Agreement, over a period of almost twelve
years should have been accepted by the Board as evidence of the proper interpretation of the agreement. The findings of the Board in Awards 1806 and
1807 were fundamentally wrong and should not be followed as a precedent.
There is no basis for the claim in this dispute, and it should be denied.
FINDINGS: The Second Division of the Adjustment Board, upon the
whole record and all the evidence, finds that:
The carrier or carriers and the employe or employes involved in this
dispute are respectively carrier and employe within the meaning of the Railway
Labor Act, as approved June
21, 1934.
This Division of the Adjustment Board has jurisdiction over the dispute
involved herein.
The parties to this dispute were given due notice of hearing thereon.
Disposition of this claim is governed by our Award No. 2440 (Docket No.
1996).
2452-14
27
AWARD
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of SECOND DIVISION
ATTEST: Harry J. Sassaman
Executive Secretary
Dated at Chicago, Illinois, this 3rd day of June, 1957.
DISSENT OF LABOR MEMBERS TO AWARDS NOS. 2440, 2441,
2442, 2443, 2444, 2445, 2446, 2447, 2448, 2449, 2450, 2451,
2452, 2453, 2454, 2455, 2456, 2457, 2504.
We are constrained to dissent from the majority findings in the aboveenumerated awards for the reasons set forth in our dissents to Awards Nos.
2083, 2084, 2197, 2205, 2230, and 2243.
It is our considered opinion that Awards Nos. 1514, 1806, and 1807 of
the Second Division should have been followed and the overtime rates embodied
in the schedule agreements should have been applied.
R. W. Blake
Charles E. Goodlin
T. E. Losey
Edward W. Wiesner
James B. Zink