NATIONAL RAILROAD ADJUSTMENT BOARD
PARTIES TO DISPUTE:
SYSTEM FEDERATION NO. 122, RAILWAY EMPLOYES'
DEPARTMENT, AFL-CIO (Electrical Workers)
THE PULLMAN COMPANY
DISPUTE:
CLAIM OF EMPLOYES:
1. That under the current agreement the Pullman Company
failed to reduce and adjust their Battery Electrical Force at the
Buffalo Shop in accord with seniority.
2. That, accordingly, the Pullman Company be ordered to compensate Electricians J. J. Troidl, J. H. Johnson and S. Mitchell for
each day that they permitted a junior Electrician to them to work.
STATEMENT:
The above question was submitted to the Second Division of the National Railroad Adjustment Board by the above referred to
organization in ex parte form, and the Division is now in receipt of a request
from employes that the case be withdrawn.
AWARD
Claim dismissed.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of SECOND DIVISION
ATTEST: Harry J. Sassaman
Executive Secretary
Dated at Chicago, Illinois, this 4th day of September, 1957.
[353]