Award No. 2614
Docket No. 1818
2-IC-EW '57
NATIONAL RAILROAD ADJUSTMENT BOARD
SECOND DIVISION
The Second Division consisted of the regular members and in
addition Referee J. Glenn Donaldson when award was rendered.
PARTIES TO DISPUTE:
SYSTEM FEDERATION NO. 99, RAILWAY EMPLOYES'
DEPARTMENT, AFL (Electrical Workers)
ILLINOIS CENTRAL RAILROAD COMPANY
DISPUTES: CLAIM OF E3WLOYES:
1. That under the current agreement other than Electrical
Workers of the Maintenance of Equipment Department were improperly used to install a Three-Inch Conduit and a Square D Switch in
the Paint Shop at Burnside Shop on October 15 and 16, 1951.
2. That accordingly the Carrier be ordered to additionally compensate Electricians C. Benson, R. Ziegner, I. M. Roll, W. E. Taylor,
Victor Spindler and W. S. McLaren in the amount of 48 hours pay
at the time and one-half rate divided amongst them.
FINDINGS: The Second Division of the Adjustment Board, upon the
whole record and all the evidence, finds that:
The carrier or carriers and the employe or employes involved in this
dispute are respectively carrier and employe within the meaning of the
Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the dispute
involved herein.
The parties to said dispute were given due notice of hearing thereon.
This dispute, once remanded in Award No. 1970, to the parties for
settlement attempt was returned for decision.
It would appear from subsequent submissions that the work in question
was under the jurisdiction of the Maintenance of Way and Structures Department, Electrical Workers.
[502]
2614-2
503
AWARD
Claims denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of SECOND DIVISION
ATTEST: Harry J. Sassaman
Executive Secretary
Dated at Chicago, Illinois, this 12th day of September, 1957.