NATIONAL RAILROAD ADJUSTMENT BOARD
The Second Division consisted of the regular members and in
addition Referee Livingston Smith when the award was rendered.
PARTIES TO DISPUTE
SYSTEM FEDERATION -NO. 150, RAILWAY EMPLOYES'
DEPARTMENT, AFL-CIO (Sheet Metal Workers)
THE CINCINNATI UNION TERMINAL COMPANY
DISPUTE:
CLAIM OF EMPLOYES:
1. That the Carrier failed to comply with the procedural provisions of the current agreement.
2. That under the current agreement other than Sheet Metal
Workers were improperly assigned to perform the work of renewing,
repairing, disconnecting, connecting, reflaring of pipe joints, renewing
pipe fittings and connections on water pipes to air condition equipment on L&N Coach 1904, February il, 1956.
3. That accordingly the Carrier be ordered to pay the claim as
presented, which was in the amount of eight (8) hours pay at the
applicable overtime rate to Sheet Metal Worker R. Rucklos for
February 11, 1956.
FINDINGS: The Second Division of the Adjustment Board, upon the
whole record and all the evidence, finds that:
The carrier or carriers and the employe or employes involved in this
dispute are respectively carrier and employe within the meaning of the
Railway Labor Act, as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the dispute
involved herein.
The parties to said dispute were given due notice of hearing thereon.
The facts and circumstances as well as the parties being similar to those
herein, disposition of this claim is governed by our Award No. 2747. (Docket
No. 2593 CUT-SM).
[268]
2772-2
269
AWARD
Remanded to the parties for further handling in accordance with the provisions of the jurisdictional dispute agreement.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of SECOND DIVISION
ATTEST: Harry J. Sassaman
Executive Secretary
Dated at Chicago, Illinois, this 20th day of February, 1958.