NATIONAL RAILROAD ADJUSTMENT BOARD
PARTIES TO DISPUTE
SYSTEM FEDERATION NO. 99, RAILWAY EMPLOYES'
DEPARTMENT, AFL-CIO (Electrical Workers)
ILLINOIS CENTRAL RAILROAD COMPANY
DISPUTE: CLAIM OF EMPLOYES:
1. That under the current Agreement the Carrier improperly assigned other than Electrical Workers of the Maintenance of Equipment Department to perform installation of a 200 volt A.C. line and
conduit in the electrical shop, Burnside Shops, on September 29, 1956,
thereby damaging Electrical Workers of the Maintenance of Equipment Department in the amount of thirty-six man hours of work and
that, accordingly, the Carrier be ordered to discontinue such practice.
2. That the following regularly employed employes of the Carrier of the Maintenance of Equipment Department be compensated at
the applicable time and one-half rate for each man hour worked
which they were entitled to perform under the applicable rules of the
current agreement.
J. Olson
R. O'Brien
R. Karas
STATEMENT:
The above question was submitted to the Second Division
of the National Railroad Adjustment Board by the above referred to organization in ex parte form, and the Division is now in receipt of a request from the
employes that the case be withdrawn.
AWARD
Claim dismissed.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of SECOND DIVISION
ATTEST: Harry J. Sassaman
Executive Secretary
Dated at Chicago, Illinois, this 6th day of March, 1958.
[385]