NATIONAL RAILROAD ADJUSTMENT BOARD


              SECOND DIVISION


The Second Division consisted of the regular members and in

addition Referee D. Emmett Ferguson when the award was rendered.


PARTIES TO DISPUTE:

SYSTEM FEDERATION NO. 150, RAILWAY EMPLOYES'

DEPARTMENT, AFL-CIO (Sheet Metal Workers)


    THE CINCINNATI UNION TERMINAL COMPANY


DISPUTE: CLAIM OF EMPLOYES:

    1. That under the current agreement the Carrier improperly assigned other than Sheet Metal Workers to the work of disconnecting and connecting of all pipe connections on cold Water Pump, including the 2" water pipe flange pipe joints on L&N 2582 coach;


    2. That accordingly the Carrier be ordered to compensate Sheet Metal Workers L. Eaton and W. Ryan, each in the amount of eight (8) hours pay at the applicable overtime rate for May 3, 1956.


FINDINGS: The Second Division of the Adjustment Board, upon the whole record and all the evidence, finds that:

The carrier or carriers and the employe or employes involved in this dispute are respectively carrier and employe within the meaning of the Railway Labor Act as approved June 21, 1934.

This Division of the Adjustment Board has jurisdiction over the dispute involved herein.

    The parties to said dispute were given due notice of hearing thereon.


This dispute is identical to that decided in our Award No. 2864 (Docket No. 2778) .

                  [4627

2870-2 463

                  AWARD


    Cause remanded as per findings.


              NATIONAL RAILROAD ADJUSTMENT BOARD By Order of SECOND DIVISION


ATTEST: Harry J. Sassaman
Executive Secretary

Dated at Chicago, Illinois, this 23rd day of May, 1958.