NATIONAL RAILROAD ADJUSTMENT BOARD
PARTIES TO DISPUTE:
SYSTEM FEDERATION NO. 97, RAILWAY EMPLOYES'
DEPARTMENT, A. F. of
L.-C.
I. O. (Electrical Workers)
ATCHISON, TOPEKA AND SANTA FE RAILWAY COMPANY
DISPUTE:
CLAIN OF EMPLOYES:
1. That under the current agreement the Carrier erred,
when they failed to compensate Communications Department Electrical Workers, R. K. Williams, V. L. Wheeler, P. C. Perry,
W. T. Hooper, T. A. Wheeler, M. A. Jontra, J. D. Scheve, E. R.
Harbord, H. L. Walker, J. E. Bandy and W. D. Hill, one and
one-half
(11/2)
hours at their regular straight time rate. Waiting
time November 26, 1957.
2. That accordingly, the Carrier be ordered ,to pay R. K.
Williams, V. L. Wheeler, P. C. Perry, W. T. Hooper, T. A.
Wheeler, M. A. Jontra, J. D. Scheve, E. R. Harbord, H. L. Walker,
J. E. Bandy and W. D. Hill, one and one-half
(11,z)
hours straight
time rate.
STATEMENT: The above question -,vas submitted to the Second DS=vision of the National Railroad Adjustment Board by the above referred to,
organization in ex parte form and the Division is now in receipt of a request.
from the employes that the case be withdrawn.
AWARD
Claim dismissed.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of SECOND DIVISION
ATTEST: Harry J. Sassaman
Executive Secretary
Dated at Chicago, Illinois, this 23rd day of March, 1959.