Award No. 3236
Docket No. 3392
2-SLSW-MA-'59
NATIONAL RAILROAD ADJUSTMENT BOARD
SECOND DIVISION
PARTIES TO DISPUTE:
SYSTEM FEDERATION NO. 45, RAILWAY EMPLOYES'
DEPARTMENT, A. F. of L.-C. I. O. (Machinists)
ST. LOUIS SOUTHWESTERN RAILWAY LINES
DISPUTE: CLAIM OF EMPLOYES:
1. That the Carrier damaged the Machinist's craft, particularly Machinist B. J. Naylor, when on November 29, 1957, a crew
of Boilermakers were assigned to remove and re-apply the forward sand dome on Engine No. 820, at Pine Bluff, Arkansas, in
violation of rules of the controlling agreement.
2. That accordingly the Carrier be ordered to refrain from
assigning other than Machinists to the removal and application of
sand domes or boxes that have as their purpose the sanding of
rails.
3. And that the Carrier be ordered to compensate Machinist
B. J. Naylor for seven (7) days at the applicable machinists' rate
for period between November 29 and December 5, 1957.
STATEMENT: The above question was submitted to the Second
Division of the National Railroad Adjustment Board by the above referred
to organization in ex parte form and the Division is now in receipt of a request from the employes that the case be withdrawn.
AWARD
Claim dismissed.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of SECOND DIVISION
ATTEST: Harry J. Sassaman
Executive Secretary
Dated at Chicago, Illinois, this 11th day of June 1959
[2597