NATIONAL RAILROAD ADJUSTMENT BOARD
PARTIES TO DISPUTE
SYSTEM FEDERATION NO. 2, RAILWAY EMPLOYES'
DEPARTMENT, A. F. of L.-C. I. O. (Electrical Workers)
MISSOURI PACIFIC RAILROAD COMPANY
DISPUTE: CLAIM OF EMPLOYES:
1. The controlling agreement, particularly Rule 26, was violated when
Telephone Maintainer Supervisor, Mr. A. Highfill, performed telephone maintainers' work on September 14, 17, 24 and October 5,
1959.
2. That accordingly the Missouri Pacific Railroad Company compensate the following named telephone maintainers in the amount of
one four (4) hour call on the dates appearing next to their names
when Supervisor Highfill performed work belonging to the Electricians Craft:
R. D. Babylon September 14, 1959
R. E. Young September 17, 1959
J. C. Schaiff, Jr. September 24, 1959
O. W. Frazier October 5, 1959
STATEMENT: The above question was submitted to the Second Division
of the National Railroad Adjustment Board by the above referred to organization in ex parte form, hearing thereon was waived, and the Division is now in
receipt of a request from the employes that the case be withdrawn.
AWARD
Claim dismissed.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of SECOND DIVISION
ATTEST: Harry J. Sassaman
Executive Secretary
Dated at Chicago, Illinois, this 12th day of June 1961.