The Second Division consisted of the regular members and in

addition Referee James P. Carey, Jr. when award was rendered.


PARTIES TO DISPUTE:

SYSTEM FEDERATION NO. 66, RAILWAY EMPLOYES'

DEPARTMENT, A. F. of L.-C. I. O. (Machinists)








EMPLOYES' STATEMENT OF FACTS: On the date and time spelled out in the employes' dispute, the carrier notified each claimant that he would be relieved of his regularly assigned duties at once on the second shift at Fond du Lac, this because of an electric power failure to said carrier.

On or about 6:30 P. M., same date, the carrier called the claimants at their homes and requested that they return to work. The carrier then took the position said claimants involved in this instant case were not entitled to compensation between the hours of 4:30 P. M. and 6:30 P. M.

Therefore, because of said carrier's position, time claims and grievances were filed on behalf of said claimants in this instant dispute and respectfully


3804--6 564



Rule 69 referred to is comparable to carrier's Rule 26 and Rule 48 referred to is comparable to carrier's Rule 23.


In summary, carrier's position is this: The electrical power interruption constituted an emergency. The shut down of shops, due to such emergencies, and the time allowance when shops are so closed is governed by Rule 26. Under Rule 26 carrier may release employes immediately. Only those employes required to work during the shutdown are entitled to payment. Claimants were not required to work between 4:30 P. M. and 6:30 P. M. Claimants were paid for all time actually worked or held on duty.


All data submitted in support of the carrier's position has been presented to the committee and made a part of the particular question in dispute.


Carrier contends that the claim is not supported by the rules and respectfully requests that it be denied.


FINDINGS: The Second Division of the Adjustment Board, upon the whole record and all the evidence, finds that:


The carrier or carriers and the employe or employes involved in this dispute are respectively carrier and employe within the meaning of the Railway Labor Act as approved June 21, 1934.


This Division of the Adjustment Board has jurisdiction over the dispute involved herein.




On September 19 1957 an electrical storm struck North Fond du Lac, Wisconsin, at about 3:30 P. M., resulting in a temporary shutdown of electric power to the carrier's shop facilities at that point. Claimants were employed in the locomotive repair shop on the second shift, 4 P. M. - 12 Midnight. After unsuccessfully attempting to ascertain the probable duration of the shutdown, the carrier suspended shop operations and sent the second shift employes home except for a few who were needed for running repairs. Power was restored about 5:30 P. M., and claimants were recalled and reported at 6:30 P. M. They were paid time from 4:00 to 4:30 P. M., and from 6:30 P. M. to the end of their shift. They claim pay for two hours of duty on account of the emergency.


The claim is based on the premise that these employes were furloughed without prior notice required by the rules.





3804-7 565

Under this rule it is said the parties impliedly acknowledged that employes excused from work because of emergency shut down due to floods, fires and the like are not entitled to advance notice or to pay for time not worked.


Rule 23 of the shop crafts agreement provides that when it is necessary to lay off employes for any reason, four work days' notice will be given employes affected before reduction is made.


There appears to be some measure of support for the carrier's position that Rule 26, which is concerned with emergencies, should be construed to provide certain exceptions to the 4 days' notice requirement of Rule 23. It will be noted, however, that unlike the factual basis presented in Award No. 1701, a supplemental agreement dated August 21, 1954, was entered into by the parties in this case. Article VI thereof reads:



The carrier maintains that Article VI of the August 21, 1954 agreement did not impose advance notice requirements where none had previously existed. We do not so construe it. It reduces advance notice of abolishing positions or making force reductions to sixteen hours. In that respect it modified Rule 23. But it goes beyond the sphere of force reduction and job abolition, and provides for 16 hours' advance notice in emergencies which require suspension of operations in whole or in part. These emergencies include not only such occurrences as are commonly regarded as Acts of God, but also strikes.


In view of the broad sweep of Article VI, we conclude that the storm at North Fond du Lac on September 19, 1957 which required the temporary shutdown of the carrier's shops was within the purview of its advance notice requirement and no notice having been given, claimants should have been paid the two hours in question at pro rata rate.










Dated at Chicago, Illinois, this 27th day of June, 1961.