The Second Division consisted of the regular members and in ad

dition Referee Charles W. Anrod when the award was rendered.


PARTIES TO DISPUTE:

SYSTEM FEDERATION NO. 101, RAILWAY EMPLOYES'

DEPARTMENT, A. F. of L.-C. I. O. (Machinists)




DISPUTE: CLAIM OF EMPLOYES: 1. That other than Great Northern Railway Machinists were used in violation of the current agreement to perform Machinists work on crane R-1839 on June 30, 1959.


2. That the Carrier therefore be ordered to compensate Hillyard Shop Machinists Samuel G. Osso and Donald E. Burbank each in the amount of eight hours' pay at the applicable rate of time and one-half.


EMPLOYES' .STATEMENT OF FACTS: The Great Northern Railway Company, hereinafter referred to as the carrier, employs machinists at its Hillyard Shop to perform, among other things, the work involved in this dispute. Among the machinists employed at Hillyard are Samuel G. Osso and Donald E. Burbank, hereinafter referred to as the claimants.


On June 30, 1959, the crane operator and a truck driver performed machinists repair work on crane R-1839 in that they repaired the crane by removing the worn out vertical and horizontal drive shafts and gears from said crane and replaced and adjusted new and reuseable parts in the crane.


This dispute was handled with all carrier officials designated to handle disputes, all of whom declined to adjust it.


The Agreement effective September 1, 1949, as subsequently amended, is controlling.


POSITION OF EMPLOYES: It is submitted that the foregoing statement of dispute is adequately supported by the terms of the aforementioned agreement made in good faith between the Carrier and System Federation No. 101 in pursuance to the amended Railway Labor Act because:





3957-10 64-4



FINDINGS: The Second Division of the Adjustment Board, upon the whole record and all the evidence, finds that:


The carrier or carriers and the employe or employes involved in this dispute are respectively carrier and employe within the meaning of the Railway Labor Act as approved June 21, 1934.


This Division of the Adjustment Board has jurisdiction over the dispute involved herein.






On June 30, 1959, it `vas discovered that the vertical and horizontal drive shafts and, as contended by the Organization in its submission brief, the gears of Machine R-1839, a large off-track crawler combination crane and shovel, were in need of repair. At that time, the machine was working on Bridge and Building (B&B) Department work at an on-line location several miles away from the Carrier's Hillyard shop, Spokane, Washington. The machine operator and a B&B truck driver, both maintenance of way employes, removed the inoperative parts from the machine. Said parts were then taken by a B&B Department employe to the Hillyard shop where they were repaired by machinists S. G. Osso and D. F. Burbank, the Claimants in this case. After the necessary repairs were made by them, the B&B Department employe returned the repaired parts to the work location of the machine and replaced them thereon.


The Claimants contend that employes other than machinists employed by the Carrier were improperly used in the above described instance to perform machinists' work. Each of them requests, therefore, eight hours' pay at the rate of time and one-half.


For the reasons hereinafter stated, we are of the opinion that the instant claim is without merit.


The uncontroverted evidence proves that the maintenance of way employes performed no repair work on the defective parts in question and that the Claimants actually repaired said parts. All that the maintenance of way employes did was to remove the inoperative parts from the machine, transport them to and from the Hillyard shop, and re-install the repaired parts on the machine. The work performed by them merely involved some simple routine tasks occurring in the day-to-day handling of the machine. It is neither asserted by the Claimants nor does the available evidence show that said work required any experience, skill or training within the contemplation of Rule 48 of the labor agreement. In other words, it was purely incidental to the actual repair work. Consequently, the work here in dispute was not covered by Rule 49 of the agreement and did not, therefore, come under the exclusive

3957-11 675

jurisdiction of the machinists' craft. See: Awards 1000, 1996, 2223, and 3824 of this Division.


For the above stated reasons, it becomes unnecessary to rule on the Carrier's contention that the assignment of the work here complained of to. employes other than machinists was sanctioned by past practice and we express no opinion on the validity of said contention.





Executive Secretary Dated at Chicago, Illinois, this 28th day of February, 1962.







The work involved in these two disputes was specifically the dismantling and installing of hoist unit and an oil pump. There is no provision in the governing agreement to exclude any assembling, maintaining, dismantling and installing regardless of the amount of such work.











The majority disregarded the agreement governing the performance of: this work. Therefor the awards are in error.