PARTIES TO DISPUTE

SYSTEM FEDERATION NO. 152, RAILWAY EMPLOYES'

DEPARTMENT, A. F. of L. - C. I. O. (Machinists)




DISPUTE: CLAIM OF EMPLOYES: 1. That the Carrier violated Article X of the Scope of the Agreement signed in Philadelphia, Pennsylvania, September 12, 1960, effective October 15, 1960, when it assigned Carman Craft employes to dismantle and assemble hoists at Samuel Rea Shop, on February 21, 1961.


2. That the Carrier be ordered to compensate C. M. Brown, A. N. Moist, J. E. Clossin and C. L. McCreary, Machinists, each eight (8) hours Grade "C" rate of pay for February 21, 1961, account of not being permitted to perform the work mentioned above.


STATEMENT: The above question was submitted to the Second Division of the National Railroad Adjustment Board by the above referred to organization in ex parte form. Parties to said dispute were given due notice of hearing thereon, and the Division is now in receipt of a request from the Employes that the case be withdrawn.










Dated at Chicago, Illinois, this 21st day of February, 1963.