The Second Division consisted of the regular members and in
addition Referee Howard A. Johnson when award was rendered.
SYSTEM FEDERATION NO. 17, RAILWAY EMPLOYES'
DEPARTMENT, A. F. of L.-C. I. O. (Carmen)
THE NEW YORK, NEW HAVEN & HARTFORD RAILROAD
COMPANY
EMPLOYES' STATEMENT OF FACTS: On Tuesday, December 16, 1958, Train No. KN-1 was derailed at East Taunton, Massachusetts, tying up main line service between Providence, Rhode Island, Taunton and Middleboro, Massachusetts. This derailment having occurred in so-called "Boston Territory", the wrecking outfit and crew of the South Boston Passenger Car Yard was called out.
To augment the South Boston outfit an crew the carrier contracted with the McCabe Sand and Gravel Company, of Taunton, Mass., called the Taunton Sand and Gravel Company in the original claim entered by the employes, for the use of a Caterpillar Crane, manned and operated by the employes of the McCabe Sand and Gravel Company.
This outfit and crew assisted and worked with the South Boston wrecking outfit and crew the following days and hours:
This dispute has been handled with the carrier officials up to and including the highest official designated to handle such disputes, on this property, all of whom having declined to adjust the matter.
The agreement of September 1, 1349, as subsequently amended, is controlling.
POSITION OF EMPLOYES: It is submitted that under the foregoing facts and the provisions of the controlling agreement, copy of which is on file with your Board, pertinent to the current dispute:
The rerailing and removing of damaged cars, at this derailment, for which the Caterpillar Crane, owned by the McCabe Sand and Gravel Co., 4222-7 22
The McCabe crane and operator were engaged at the scene of wreck in the instant dispute for three hours on December 16 and for 91/z hours on December X17 contrary to allegations of the Brotherhood that they were so engaged for nine hours on December 16, ten hours on December 17 and six hours on December 18 (The latter date they performed no service).
The carrier or carriers and the employe or employes involved in this dispute are respectively carrier and employe within the meaning of the Railavay Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the dispute involved herein.
The Carrier alleges that the Providence Wrecking Outfit could not have been used; that it would have had to come around in back of the Boston Wrecking Outfit east of the derailment because there was no siding and no area at the west end of the wreck for disposal of rerailed cars; that in any event it would have been necessary to rent the McCabe Company highway crane for work which (for reasons not further specified), its own equipment could not practicably have accomplished; that it was not unusual to rent necessary equipment of types seldom used and therefore uneconomical to own; and finally that the blockage of the single line main track constituted an emergency warranting use of the McCabe crane.
The Employes deny all these allegations except the lack of a siding at the west end of the derailment; and allege that the work performed by the rented crane was the same as that regularly performed by Carrier's cranes from both ends of derailments and could have been so performed by them in this instance; and that the Carrier's use of 65 hours' elapsed time to clear the wreck during three days, with discontinuation of work on both intervening nights, negatives the existence of an emergency situation.
The Carrier did not show how the lack of a siding west of the derailment made a condition different from that at any wreck on a single track line where there happens to be no siding, or why such other wrecks do not necessitate an off-track crane; and certainly its leisurely clearing of the wreck does not indicate emergency conditions.
We cannot conclude from the record that when it found additional help desirable the Carrier was justified in using outside equipment and forces instead of its own most readily available outfit. Presumably the Providence outfit would have been used on approximately the same basis as the Boston outfit. Therefore Claim 1 must be sustained as to December 16 and 17, 1958, but denied as to December 18, on which the McCabe crane admittedly was not used.
Claim 2 seeks payment to the members of the Providence Wrecking Crew of specific amounts claimed to be the differences between what each actually received and what he would have received during the three days' period. The record does not show how those amounts were computed or allocated, and it is conceded that the McCabe crane was not used on the 18th. Claim 2 must therefore be remanded to the property for ascertainment of the amount, if any, payable to each claimant herein at the straight time rate for the time not worked.
Claim 1 sustained as to December 16 and 17, but denied as to December 18, 1958. 4222-9 24