Award No. 4296
Docket No. 4117
2-EJ&E-EW '63
NATIONAL RAILROAD ADJUSTMENT BOARD
SECOND DIVISION
The Second Division consisted of the regular members and in
addition Referee J. Harvey Daly when the award was rendered.
PARTIES TO DISPUTE
SYSTEM FEDERATION NO. 20, RAILWAY EMPLOYES'
DEPARTMENT, A. F. of L.-C. I. O. (Electrical Workers)
ELGIN, JOLIET & EASTERN RAILWAY COMPANY
DISPUTE:
CLAIM OF EMPLOYES:
(a) That the Carrier violated the current agreement when they
permitted the National Electric Coil Company to repair eight traction
motors.
(b) That accordingly, the Carrier be ordered to compensate
Electricians R. Hummo, L. Kenney, L. Eichelberger, J. Buffo,
F.
Zabkar, V. Camel, C. Colegrove, C. Lumyahn, W. Krnac, A. D'Ottavio,
R. Sackman, J. Paul, A. Cormier, W. Stonex, and
F.
White each in
the amount of 32 hours at the straight time rate of pay.
EMPLOYES' STATEMENT OF FACTS:
Three years ago the Elgin,
Joliet and Eastern Railway Company, hereinafter referred to as the carrier,
installed a traction motor assembly line in their electric shop at Joliet, Illinois.
This assembly line has upgraded 98 traction motors and repaired 194 traction
motors for a total of 292 traction motors upgraded and repaired.
The carrier instead of permitting their employ es working on the assembly
line to upgrade and repair traction motors serial and model number D27-3986,
D27B-4143, D17B-9963, D27B-262A, D17B-303A, D7-43K4635, D27B-52K613
and D27B-49D542, sent four (4) of these motors on August 10, 1960, and the
other four (4) on September 2, 1960, to the National Electric Coil Company,
who repaired and returned these same motors to the carriers locomotive shop
at Joliet, Illinois.
Due to this the local committee met with Mr. G. W. Burnett, Master
Mechanic, and submitted a claim charging violation of the current agreement.
Mr. Burnett under date of October 28, 1960, denied this claim on the basis that
all electricians available were working and that a General Rule pertaining to
sending work out to other companies covered this claim.
Under date of November 15, 1960, we appealed Mr. Burnett's denial to Mr.
C. G. Mahoney, Superintendent of Motive Power advising that Rule 30 permitted only employes of the carrier to perform the work involved.
[39]
4296-15
valid reasons for its action in sending out the involved traction motor repair
work. It has not followed or pursued an unusual course for the evident purpose
of depriving employes of the work which they ordinarily and traditionally
perform. (Award No. 2377)
The work herein involved which was performed by National Electric Coil
is to be considered as a whole and may not be subdivided for the purpose of
determining whether some parts were within the capacity of the carrier's
forces
(Awards 3206, 4776, 4954, 5304, 5563 of the Third Division.)
This work was properly performed by National Electric Coil because it
required special skills, equipment, and the work was unusual and novel in
character as far as claimants were concerned.
(Awards 757, 2338, 2465, 3206,
4712, 4776, 5028, 5151, 5304, 5563 and 6492 of the Third Division.)
These same principles were set forth by Referee Carter in Second Division
Award No. 1808; and he diligently followed them in Award No. 2377.
In conclusion, the carrier submits that no contractual right of the claimants was abridged when the involved traction motors were sent out for
repairs. The claimants never have performed the required work; they are not
qualified to perform it; and we do not have the special equipment and machinery to do it. It would be gross error to hold this carrier, the "J", to the same
.standards and principles that are applicable on large carriers whose size
permits adequate qualified personnel and complete traction motor repair
facilities. Sustaining awards on such carriers are irrelevant and immaterial to
the proper determination of the instant dispute. Specifically in point, there. is
no competent authority in support of the organization's far sweeping position.
For all of the above shown reasons, there is no semblance of merit in this
.claim. Accordingly, it should be denied in its entirety by the Board.
FINDINGS: The Second Division of the Adjustment Board, upon the
whole record and all the evidence, finds that:
The carrier or carriers and the employe or employes involved in this
dispute are respectively carrier and employe within the meaning of the Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the dispute
involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
On August 10, 1960 and on September 2, 1960, the Carrier sent-on each
date-four traction motors on a repair and return basis to the National
Electric Coil Company, Columbus, Ohio. The traction motors were repaired
and returned to the Carrier on August 26, 1960 and September 20, 1960,
respectively.
Rule 30, pertaining to mechanics and apprentices, and Rule 114, pertaining
to electricians, are the principal rules involved in this dispute.
In the instant case, the record shows that for approximately twenty-five
years-since dieselization was initiated in 1936-the Carrier has followed the
practice of having traction motor repairs performed by outside companies on
repair and return basis and on a unit exchange and warranty basis. In 1957
the Carrier's improved traction motor reapir program permitted the Carrier to
4296-16
54
perform more traction motor repair work than heretofore. It did not, however,
according to the Carrier, eliminate the necessity for sending out traction
motors on a repair and return basis. In fact, the Organization did not successfully refute the Carrier's statement that since 1957 the Carrier had sent
out eighty-one traction motors on a repair and return basis.
It is a well-established rule that a Carrier cannot contract out work
coming within the scope of collective agreements. However, exceptions to that
rule are permissible when it is shown that the work contracted out requires
equipment and skills not possessed by the Carrier.
The record indicates that the Carrier has not followed or pursued a course
for the obvious purpose of depriving employes of work which they customarily
and traditionally perform. The Carrier stated that it "readily recognized that
it cannot indiscriminately send out work that might be performed on this
property".
The Carrier attempted to justify its actions on the basis of past practice,
lack of special shop equipment and lack of requisite electrical skills by its
electricians.
Claims and contentions contrary to the Carrier's position must be supported by factual proof in order to overcome managerial judgments and
prerogatives in contracting out work. A carrier's managerial judgment cannot
be lightly regarded because of the burden the Carrier assumes as a public
carrier and also because of its responsibility to its employes.
It is, of course., the responsibility of the Organization to disprove the
Carrier's contentions and statements. In this case, the Board believes that the
Organization failed to sustain that burden of proof. It is true that the Organization presented proof in its rebuttal statement, but it is the Board's disposition that such evidence must be raised and introduced on the property and
included in the initial submission to the Board, otherwise it is inadmissible.
AWARD
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of SECOND DIVISION
ATTEST: Harry J. Sassaman
Executive Secretary
Dated at Chicago, Illinois, this 27th day of September, 1963.
DISSENT OF LABOR MEMBERS TO AWARD NUMBER 4296
The findings
in this Award are not in keeping with the record as the
Employes' Exhibit A attached to their submission is a copy of the Master
Mechanic's decision to the Employes on the initial claim and reads in part
as follows:
"Your time claim as listed below will be processed under the
following case number.
4296-17
55
NX-6-60 Claim for 480 man hours account of eight (8) EMDD-7, D-17, D-27 Traction Motors sent to National Coil: four (4) on
August 10, 1960, returned August 26, 1960 and four (4) sent September 2, 1960, returned September 20, 1960.
The Electricians' Committee claim the Carrier is in violation of
Rule 114 of the Electrical Rules, also that the work is done on the
property and has been for some time, that it is desirous to retain the
work here.
The above claim denied on the basis all Electricians available
are working, also General Rule pertaining to sending work out to
other Companies covers this claim." (Emphasis ours.)
As you can see from the above quote the Carrier's position points out that
the Local Committee has claimed from the start that the work involved has
been performed on the property and that they intended to retain the work for
the employes they represent in keeping with the rules of the Agreement. The
Carrier denied the claim stating that all Electricians available were working
and that a general rule pertaining to the sending out of work to other companies covered this claim.
The Employes' Exhibit B attached to their submission is the General
Chairman D'Ottavio's appeal to Superintendent of Motor Power pointing out
that the Electricians on the property have always performed this work and
that the Carrier even set up an assembly line in their Electrical Shop for the
purpose of repairing and rebuilding traction motors and also pointing out that
the traction motors involved in this dispute were returned to the Carrier by
the National Coil Company and were still unused and laying on the Locomotive
Shop floor. This Exhibit reads in part as follows
"Rule 114 states electricians' work shall consist of repairing, rebuilding, installing, inspecting and maintaining the electric wiring
of generators, switchboards, motors and control, etc. We have always
performed this work and as you know we have a traction motor
assembly line in the electric shop to install coils and to repair and
rebuild traction motors. The motors in question after being returned
from National Coil Co., are still unused on the floor in the locomotive
shop more than a month after being returned." (Emphasis ours.)
"Rule 30 assignment of work rule states in part, "None but
mechanics or apprentices regularly employed as such shall do
mechanics work as per special rules of each craft . . ." We were hired
and assigned by this carrier to perform this work, we also have the
men and the facilities to perform this work." (Emphasis ours.)
The Employes' Exhibit C attached to their submission is the Superintendent of Motor Power's denial of the appeal and it reads in part as follows:
"Be advised that the matter of this claim has been investigated
and it is determined that during the time the motors were sent out for
repairs the Carrier was having difficulty in producing the electrical
work needed with the number of people employed, same because of
shortage of electricians, in that heavy repairs were being made to
locomotives, 102, 114 and 415, and that not enough Westinghouse
Model 3'70 traction motors were being produced in the Joliet Shop to
handle the needs of Class 5 repairs to road locomotive trucks nor to
take care of the road failures of No. 370 Model traction motors.
4296-18
56
The time claim in question is respectfully declined. As pointed
out above, a shortage of electricians existed, and the Carrier is allowed
by rule the right to purchase new or have equipment repaired at outside concerns." (Emphasis ours.)
The Carrier again denied the claim on the basis that there was a shortage
of Electricians that the Electricians were fully occupied and were unable to
produce enough traction motors to take care of the heavy repairs being made
ands that they were allowed by a rule to purchase new or to have equipment
repaired at outside concerns. However, the Carrier still failed to point out what
rule gives them this right. And admitted that the employes did do heavy
repairs.
The Employes' Exhibit D attached to their submission is the General
Chairman's appeal to the Chief Mechanical
Officer and reads in part as follows:
"It is my opinion that the carrier has violated the electrical
workers special rule 114, and the shop crafts general rule 30.
We have always performed this work, and as you know, we have
a traction motor assembly line in the electric shop to install coils and
to repair and rebuild traction motors. The motors in question after
being returned from National Coil Co. were unused on the floor of
locomotive shop for two months after being returned.
The caxrier has taken the position that it had a shortage of
electricians, yet a total of 10 or more electricians have applied for
employment and have been interviewed by Div. Electrical foreman
this past summer and fall, and have been turned down. Among these
one of our own electricians, a lineman who was furloughed from M. of
W. Dept. and recommended by Mr. Waltz, signal engineer. This man
had seven years of electrical experience." (Emphasis ours.)
As you can see the. Employes pointed out again that the Electricians on
the property have always performed this work and refers to the traction motor
assembly line that was established by the Carrier to perform this work. He
also refers the Carrier to Rules 30 and 114 which supports his position that the
Carrier was violating the Agreement. He also pointed out that ten electricians
applied for employment, all were turned down and that one of these. Electricians was an Electrician, in the employ of the Carrier, who was on furlough.
The Employes' Exhibit E attached to their submission is the Chief
Mechanical Officer's denial of the appeal and reads in part as follows
"I have investigated the circumstances concerning this incident
and find that despite the fact that all electricians on the E.J. &, E.
were fully employed by the railroad, and that a number of them were
repairing traction motors, they were unable to repair a sufficient
number to meet the needs of the service. There were a considerable
number of trucks torn down in the shop awaiting traction motors
before they could be rebuilt, and there were a number of locomotives
running on the railroad with wheels in worn condition necessitating
changeout of wheels and motors in the immediate future. In view of
this predicament it was imperative for the railroad to send out the
eight traction motors to relieve the congestion in the shop and to be
able to maintain the locomotives in satisfactory operating condition
in compliance with ICC rules and regulations.
4296-19
57
"This work is specifically work of the shop craft electricians. The
electrical workers of this Carrier have always performed this work.
About 3 years ago the Carrier installed a traction motor assembly
line in the electric shop for the sole purpose of installing coils, and to
repair and rebuild traction motors, the motors in question after being
returned from National Coil Co. were unused on the floor in the
locomotive shop for two months.
Rule 30 Assignment of Work Rule states in part, 'none but
mechanics or apprentices regularly employed as such shall do
mechanics work as per special rules of each craft.' We. were hired
and assigned by the Carrier to perform this work.
The Carrier has taken the position that it had a shortage of
electricians, as far back as 5 to 8 years ago, the total number of shop
and roundhouse electricians did not exceed 20 without motor assembly
line or locomotive rewiring, today we have the same amount of electricians, with added work such as traction motor assembly line and
heavy locomotive rewiring work, at the present time rewiring 3 locomotives at a time.
In Bachman's letter of December 23, 1960, declining this claim
he states 'during this period a determined effort was made to hire
electricians.' It is my opinion that a sincere effort was not made. The
ads in the Joliet Herald News were few, and during the time. in question and to this day a total of ten (10) or more electricians have
applied for employment, and have been interviewed by div. electric
foreman and have been turned down. Among these was one of our own
electricians, a lineman who was furloughed from M. of W. Dept, and
recommended by K. Waltz, Signal Engineer. This man had seven years
of electrical experience.
Bachman also states 'prior to the last two years all traction
motors were sent out of the E.J. & E. shops to various contract shops
for repairs'. I cannot agree with this statement, although we did not
replace too many coils or mainpoles as we are now doing,
we
did tear
down and repair traction motors prior to the last two years, whenever
traction motors were sent out we were told that it was on a unit
exchange basis.
For any or all of the foregoing reasons it is my opinion that this
claim is legitimate and should be paid." (Emphasis ours.)
The Employes' Exhibit G attached to their submission is the Vice President's in Charge of Personnel, denial to the appeal, who is the top appeal
officer on the property, and reads in part as follows:
"This is in reply to your letter dated January 9, 1961, wherein you
appeal Case NX-6-60 to this office for consideration.
After reviewing all the facts in this case, it is the opinion of this
office that Mr. G. F. Bachman, Chief Mechanical Officer, adequately
stated the Carrier's position in his letter of declination to you dated
December 23, 1960. Since you have offered no additional information
or argument in your appeal, that letter of Mr. Bachman's is incorporated as a part of this reply and, for the reasons set forth therein
your claim is respectfully declined."
This proves that the Carrier on the property used three different excuses
to deny this claim and the Employes refuted each one of them, but no where
in this record up to this point did the Carrier's representatives claim that the
Employes did have the requisite electrical skills or that the Carrier lacked
special shop equipment. In fact, the Carrier admitted that the employes did
4296-20
58
the work involved but alleged that the reason they sent the work out was that
the employes could not produce sufficient number of traction motors.
However, Mr. Verd who is the top appeal officer on the property after
writing the above quoted decision which was dated February 13, 1961 he
again wrote a letter under date of March 28, 1961 to General Chairman
D'Ottavio taking another position by stating that the repair work in dispute
requires special skills not possessed by the employes and special equipment not
possessed by the Carrier and alleging that the General Chairman agreed with
this. A copy of this letter was attached to the Employes' submission and shown
as Exhibit H and reads as follows:
"March 28, 1961
Mr. Albert D'Ottavio, General Chairman
International Brotherhood of Electrical Workers
303 Youngs Avenue
Joliet, Illinois
Dear Sir:
Please refer to your letter dated February 19, 1961, wherein you
requested a conference for the purpose of discussing a claim identified
as Case NX-6-60, which reads as follows:
. . . time claim for 480 hours pay, in behalf of the following claimants, each claiming 32 hours pay for a total
of 480 man hours. R. Hummo, L. Keeney, L. Eichelberger,
J. Buffo, F. Zabkar, V. Camel, C. Colegrove, C. Dumyayn,
W. Krnac, A. D'Ottavio, R. Sackman, J. Paul, A. Cormier,
W. Stonex, and F. White, because on August 10, 1960 and
again on September 2, 1960, the carrier sent to the National
Electric Coil Co. Columbus, Ohio, via their truck, a total of
eight (8) traction motors. serial and model numbers as
follows. D27-3986, D27B-4143, D17B-9963, and D27B262A,
these were repaired and returned to locomotive shop on
August 26, 1960, serial and model numbers D17B-303A,
D7-43K4635, D27B-52K613, and D27B-49D542, were repaired
and returned to locomotive shop on September 20, 1960.
At conference in my office on March 15, 1961, this claim was
discussed.
It was the position of your Organization that the subject work is
specifically reserved to employes of the Electricians' Craft by Rule
114 of the controlling Agreement and that the Carrier violated this
Rule, as well as Rule 30, when it awarded the work of repairing
eight (8) traction motors to the National Coil Company of Columbus,
Ohio.
The Carrier answered your charges by stating that none of the
repair work performed by the National Coil Company has ever been
considered exclusively that of the employes represented by your
Organization. Furthermore, it was noted that a substantial portion
of such repair work required special skills not possessed by these
employes and special equipment not possessed by the Carrier and it
was, therefore, necessary that the work be awarded to this outside
firm.
4296-21 559
In this regard, the Carrier stated
that three of the eight
subject traction motors had been up-graded and that the
armatures and armature shafts had been repaired and dynamically balanced in all eight. When asked if Carrier's
employes had ever performed this type of repair work, you
again conceded that they had not. There were several additional repair operations performed by this outside firm which
you admitted had not been accomplished by Carrier's forces
in the past.
During our discussion, the Carrier offered records showing conclusively that repair work identical to the work performed here had
been awarded to outside firms on at least eighty-one occasions during
the past three-year period while the so-called traction motor assembly
line was in operation. This, without objection by your Organization.
The Carrier answered your remark (that members of your Organization had always been told that motors sent out to outside firms on
these eighty-one occasions were on a unit exchange basis) by stating
that they were not sent out on that basis and, further, that whatever
sources of information were available to members of your Organization on this present occasion were available also on all of the other
eighty-one occasions. Thus, the Carrier would not accept the charge
that the members of your Organization had been misinformed during
these past several years (insofar as concerns the basis on which
traction motors were sent to outside firms for repairs), nor would it
now accept the argument that your Organization would have objected
previously to this practice had the true facts been known.
In view of the foregoing, your claim is considered to be without
merit and is respectfully declined.
Very truly yours,
/s/ PAUL H. VERD
Paul H. Verd
Vice President-Personnel"
General Chairman D'Ottavio under date of April 17, 1961 replied to Mr.
Verd denying all of the allegations in his letter a copy of this letter was
attached to the Employes' Submission and shows as Exhibit I.
"Mr. Paul H. Verd,
Vice President Personnel,
Elgin, Joliet & Eastern Railway Co.,
208 So. LaSalle Street
Chicago 4, Illinois
Dear Mr. Verd:
This is in reply to your letter dated March 28, 1961, regarding
our conference held on March 15, 1961, regarding Case NX-6-60.
In your letter the following appears:
'The Carrier answered your charges by stating that none
of the repair
work performed by the National Coil Company
has ever been considered exclusively that of the employes
4296-22
60
represented by your Organization. Furthermore, it was noted
that a substantial portion of such repair work required
special skills not possessed by these employes and special
equipment not possessed by the Carrier and it was, therefore,
necessary that the work be awarded to this outside firm.'
We cannot understand the above statement that the work in
dispute required special skill and equipment, which was the reason
the work was awarded to an outside firm, as you, and all of your
subordinates have stated that the reason the motors were sent out
was that the Electrical Force was unable to repair a sufficient
number of motors to meet the needs of the service. Your letter of
decision denying our appeal in this claim, dated February 13, 1961,
reads in part, as follows:
`After reviewing all the facts in this case, it is the opinion
of this office and Mr. G. F. Bachman, Chief Mechanical Officer,
adequately stated the Carrier's position in his letter of
declination to you dated December 23, 1960. Since you have
offered no additional information or argument in your appeal,
that letter of Mr. Bachman's is incorporated as a part of
this reply and, for the reasons set forth therein, your claim
is respectfully declined.'
You stated that you declined our claim for the reasons set forth
in Mr. Bachman's letter dated December 23, 1960. There was no
mention of special skill or equipment in Mr. Bachman's letter dated
December 23, 1960. His reason for denying our claim was that the
electrical force could not repair a sufficient number of motors to meet
the needs of the service, as the following appears in this letter:
I have investigated the circumstances concerning this
incident and find that despite the fact that all electricians on
the E. J. & E. were fully employed by the railroad, and that
a number of them were repairing traction motors, they were
unable to repair a sufficient number to meet the needs of the
service. There were a considerable number of trucks torn
down in the shop awaiting traction motors before they could
be rebuilt, and there were a number of locomotives running
on the railroad with wheels in worn condition necessitating
changeout of wheels and motors in the immediate future. In
view of this predicament it was imperative for the railroad
to send out the eight traction motors to relieve the congestion
in the shop and to be able to maintain the locomotives in
satisfactory operating condition in compliance with ICC rules
and regulations.
This same reason was given by Mr. C. G. Mahoney, Supt. Motive
Power, in his letter of decision dated November 26, 1960, as the following appears in his letter:
The time claim in question is respectfully declined. As
pointed out above, a shortage of electricians existed . . .
Mr. G. W. Burnett, Master Mechanic, in his letter dated October
28, 1960 denied the claim because all electricians available were
working.
4296-23
In your decision denying our appeal dated February 13, 1961, you
agreed with Mr.
Bachman's reasons for denying your claim which was
to have these motors repaired to meet the needs of the service. In our
appeal to Mr. Bachman we pointed out to him that these motors were
returned to the locomotive shop on August 26th and September 20,
1960, and they were still unused and laying on the shop floor two
months later.
Also in your letter dated March 28, 1961, the following appears:
In this regard, the Carrier stated that three of the eight subject
traction motors had been up-graded and that the armatures and
armature shafts had been repaired and dynamically balanced in all
eight. When asked if Carrier's employes were qualified to perform this
type of repair work, you conceded that they were not. When asked if
Carrier's employes had ever performed this type of repair work, you
again conceded that they had not. There were several additional
repair operations performed by this outside firm which you admitted
had not been accomplished by Carrier's forces in the past.
I do not agree with this statement at all, as I stated in our conference, that we upgrade and do the repairs to the motors whenever
needed. The only part of the operation that I said was not performed
by us on the property before, was the dynamic balancing of the shafts,
and the only reason we do not perform this work is that the Carrier
does not have the machine necessary to do this work. We have Electricians who could qualify to perform this work if the Carrier gets the
machine necessary to do this operation.
This is just to clarify the record and to advise that we intend to
progress this claim in accordance with the Railway Labor Act as
amended.
Very truly yours,
/s/ Albert D'Ottavio
Albert D'Ottavio
General Chairman
Local 757, I. B. E. W."
This was the final handling on the property. The Carrier then in their
submission to the Board went into great detail about their shop not having
special equipment in comparison to other Carriers. This was never discussed
on the property. They also went into great detail about the skill of their employes compared with other Carrier's again, this is a matter that was not
discussed on the property. They also alleged the practice of the motors being
repaired by outside concerns for twenty-five years, which was not discussed
on the property. They also alleged that the Employes did not perform heavy
repair this again was not handled on the property. Due to this the employes
answered these allegations in their rebuttal statement as this was the first
time they knew that the Carrier was taking these positions. The Referee in
his findings accepted this from the Carrier but he declined to accept the
rebuttal statement of the employes. His findings read in part as follows:
"It is, of course, the responsibility of the Organization to disprove
the Carrier's contentions and statements. In this case, the Board
4296-24
62
believes that the Organization failed to sustain the burden of proof.
It is true that the Organization presented proof in its rebuttal statement, but it is the Board's disposition that such evidence must be
raised and introduced on the property and included in the initial
submission to the Board, otherwise it is inadmissible."
The Award is erroneous. It is based upon a determination of issues which
were not raised until the Carrier presented same in its submission. That being
the case such issues should either have been disregarded or the Organization's
rebuttal statement should likewise have been considered in view of the first
paragraph of the findings which state "The Second Division of the Adjustment
Board, upon the whole record and all the evidence, finds . . . "
The claim should have been sustained and we dissent.
/s/ E. J. McDermott
/s/ T. E. Losey
/s/ C. E. Bagwell
/s/ R. E. Stenzinger
/s/ James B. Zink