The Second Division consisted of the regular members and in

addition Referee Jacob Seidenberg when award was rendered.


PARTIES TO DISPUTE:

SYSTEM FEDERATION NO. 76, RAILWAY EMPLOYES'

DEPARTMENT, A. F. of L.-C. I. O. (Electrical Workers)


CHICAGO, MILWAUKEE, ST. PAUL & PACIFIC

RAILROAD COMPANY










4482-2 494

      6. The employes further contend that the payment for the sixth day of the work week recognized as their standby day, is to compensate them for any and all emergency service performed after their normal working hours during the work week, Saturdays included, for which no additional compensation is paid to their monthly rate of pay. They must also standby after each work day period or inform their supervisor as to where they may be reached in order to respond for emergency calls.


EMPLOYES' STATEMENT OF FACTS: Trolley Linemen Carl E. Daggett and R. T. Lane, hereinafter referred to as the claimants, are employed by the Chicago, Milwaukee, St. Paul & Pacific Railroad Company, hereinafter called the carrier, as monthly rated trolley linemen five days per week with Saturday as a standby day.


During a period both before and after September 23 and 24, 1961, the carrier was engaged in a construction project of lowering the tracks through tunnels located on lines west in its electrified main line territory. The track forces (maintenance of way) were engaged in the performance of that work and in connection therewith and during this period of construction the claimants were also engaged in performing the work on the trolley line constructing it so that it was properly located in relation to the road bed and rails.


On Saturday, September 23, 1961, which is the claimant's standby day, and on Sunday, September 24, 1961, the claimant's rest day, they, the claimants, were instructed to continue their work on this construction project and they worked eight hours on each of those days.


The carrier, in accordance with the agreement and understanding, paid the claimants for eight hours at time and one-half for working on construction work on that day, but subsequently deducted wages from their salary amounting to that claimed in the employes' statement of claim.


Prior to the occurrence of this dispute, such monthly rated employes received time and one-half, in addition to their monthly rate, for performing such work as is here involved when such work was performed on their standby days and/or rest days and was the subject of discussion and an understanding was had with Mr. A. G. Britzius, assistant to general manager, who was the highest officer of the carrier authorized to handle disputes concerning trolley linemen. (lines west.)


The claim was filed and handled in accordance with the agreement for the amount deducted and was appealed up to and including Mr. S. W. Amour, assistant to vice president, as shown by a copy of the general chairman's letter. Mr. Amour also declined to settle the case, as shown by a copy of his letter.


The agreement, effective September 1, 1949 as subsequently amended, is controlling.


POSITION OF EMPLOYES: It is respectfully submitted that based upon the foregoing statement of facts and of the aforementioned agreement, particularly Rule 29, reading:


    "Employes regularly assigned to perform road work and paid on a monthly basis shall be assigned one regular rest day per week, Sunday if possible. Rules applicable to other employes covered by this

4482-6 ,498

As there is no schedule rule or agreement which either provides or contemplates additional payment over and above the monthly rate for service performed on the sixth or standby day or days of the work week of monthly rated road service employes such as the claimants, it will be readily apparent that by the instant claim the employes are attempting to secure through the medium of a board award in the instant case something which they do not now have under the rules and in this regard we would point out that it has been conclusively held by the second division, as well as by the other three divisions and the various special boards of adjustment, that your board is not empowered to write new rules or to write new provisions into existing rules.


The carrier wishes to point out that the instant claim is one of five identical cases presently before your board, the other four cases identical to this one being Case Numbers 6293, 6295, 6296 and 6297 (the case numbers referred to above are the ones assigned to said cases by the Executive Secretary of the Second Division, National Railroad Adjustment Board). So as to not unduly burden your board the carrier attempted to persuade the employes to progress only one of the five cases to your board with the understanding that the remaining four would be held in abeyance to be disposed of on the basis of the award rendered in the one case progressed to your board; however, for some unexplained reason the employes would not enter into such an agreement with the carrier. The carrier mentions this so that your board will understand that it is through no fault of the carrier that your board is now burdened with five identical cases, instead of only one.


It is the carrier's position that there is absolutely no basis for the instant claim, and we respectfully request that it be denied.


FINDINGS: The Second Division of the Adjustment Board, upon the whole record and all the evidence, finds that:


The carrier or carriers and the employe or employes involved in this dispute are respectively carrier and employe within the meaning of the Railway Labor Act as approved June 21, 1934.


This Division of the Adjustment Board has jurisdiction over the dispute involved herein.


    Parties to said dispute waived right of appearance at hearing thereon.


    The parties to this dispute are the same as in Award No. 4481.


The facts are essentially the same as in that Award, and the submissions contain the same type of evidence and arguments.


Our Award No. 4481 governs here and the claim must be sustained in accordance therewith.

                  AWARD


    Claim sustained in accordance with above Findings.


              NATIONAL RAILROAD ADJUSTMENT BOARD By Order of SECOND DIVISION


              ATTEST: Harry J. Sassaman

              Executive Secretary


Dated at Chicago, Illinois, this 26th day of March, 1964.