DISPUTE: CLAIM OF EMPLOYES:
1. That other than the regularly assigned wrecking crew were improperly used to perform wrecking service on January 5, 1963.
2. And that, accordingly, the Carrier be ordered to compensate Carmen Jule Barnes, Don Rygh and J. P. Johnson in the amount of 4% hours
each, at the time and one-half rate account of said violation.
FINDINGS: The Second Division of the Adjustment Board, upon the whole
record and all the evidence, finds that:
The carrier or carriers and the employe or employes invloved in this dispute
are respectively carrier and employe within the meaning of the Railway Labor Act
as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the dispute involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
This claim is identical with that in Award 4821, involving the same Agreement,
in that carmen from the overtime call list were used instead of the regularly assigned
wrecking crew to perform rerailing service outside of yard limits when a derrick
was not needed.
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of SECOND DIVISION
ATTEST: Charles C. McCarthy
Executive Secretary
Dated at Chicago, Illinois, this 11th day of March, 1966.
Keenan Printing Co., Chicago, 111. Printed in U. S. A.