*m`
gas
Award No. 6010
Docket No. 5866
2-MP-CM-'70
NATIONAL RAILROAD ADJUSTMENT BOARD
SECOND DIVISION
The Second Division consisted of the regular members and in
addition
Referee Gene T. Ritter when award was rendered.
PARTIES TO DISPUTE:
SYSTEM FEDERATION NO. 2, RAILWAY EMPLOYES'
DEPARTMENT, AFL-CIO (Carmen)
MISSOURI PACIFIC RAILROAD COMPANY
DISPUTE: CLAIM OF EMPLOYES:
1. That the Missouri Pacific Railroad Company violated the
controlling agreement when they arbitrarily assigned other than
carmen (Sheet Metal Worker) to complete replacement of water
cooler in Diesel Unit No. 386 at the Greater Little Rock Terminal
on July 4, 1968.
2. That accordingly, the Missouri Pacific Railroad Company be
ordered to compensate Locomotive Carpenter R. A. Sanders in the
amount of two hours, forty minutes (2' 40") at the punitive rate
for July 4, 1968 as he was available and should have been called to
complete this work.
FINDINGS: The Second Division of the Adjustment Board, upon the
whole record and all the evidence, finds that:
The carrier or carriers and the employe or employes involved in this
dispute are respectively carrier and employe within the meaning of the
Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the dispute
involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
The issue contained in this dispute is identical to the dispute decided in
Award No. 6008. Therefore, this claim will be denied for the same reasons
as outlined in said Award No. 6008.
AWARD
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of SECOND DIVISION
ATTEST: E. A. Killeen
Executive Secretary
Dated at Chicago, Illinois, this 8th day of October, 1970.
Keenan Printing Co., Chicago, Ill. Printed in U.S.A.