(Advance copy. The usual printed copies will be sent later.)
Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No.
6362
SECOND DIVISION Docket No. 6155
2-MP-MA-t72
The Second Division consisted of the regular members and in
addition Referee Irving T. Bergman when award was rendered.
( System Federation No. 2, Railway Employes'
( Department, A. F. of L. - C. I. 0.
Parties to Dispute: ( (Machinists)
( Missouri Pacific Railroad Company
Dispute: Claim of Employes:
1. That the Missouri Pacific Railroad Company unjustly suspended Machinist
T. R. Winfrey from service for thirty (30) actual days on Wednesday,
February 18, 1970 til 12:01 A.M., Saturday, March 21, 1970, for his
responsibility in connection with failure to properly apply No. 14
connecting rod basket on Diesel Engine Unit No. 237 on January 21,
1970.
2. That accordingly, the Missouri Pacific Railroad Company be ordered
to compensate Machinist T. R. Winfrey in the amount of eight (8)
hours at the straight time rate from Wednesday, February 18, 1970 to
12:01 A.M., Saturday, March 21, 1970; also that his personal records
be cleared by letter of this discipline.
Findings:
The Second Division of the Adjustment Board, upon the whole record and
all the evidence, finds that:
The carrier or carriers and the employe or employes involved in this
dispute are respectively carrier and employe within the meaning of the Railway
Labor Act as approved June 21, 1934 . . . ..
This Division of the Adjustment Board has jurisdiction over the dispute
involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
Claimant with the aid of a machinist's helper performed the assigned work.
Two other machinists, in turn, finalized and inspected the work. The engine was
returned to the shop when it failed to operate properly. Inspection determined
that the failure occurred in the part of the engine which had been repaired..
The hearing was first scheduled. on 3 days notice but was held 10 days
after notice when the Local Chairman requested additional time. The two machinists
were given 15 days deferred suspension, the claimant was given 30 days actual
N
Form 1 Award No.
.665
Page 2 Docket No.
6
. 2 _MP-MA- ' 72
suspension and the helper '(who eras taken off the work before its completion) was
not penalized. The Organization contends that the notice did not state the charge
precisely, that not enough time was given to prepare adequately for the hearing,
that a material witness who was on vacation was not given an opportunity to testify
and that the carrier did not prove that claimant was at fault.
Rule 32 of the Agreement follows the usual Rule for reasonable notice
to the employe of the precise charge and the opportunity to produce witnesses and
to be represented.. It is usually required that the hearing be held promptly.
Three days notice may have been too short but this was corrected when the time
was extended at the request of the Local Chairman. The charge was definite and
clearly referred to the work performed which is in question. When it was read to
claimant at the hearing no further objection was raised and the claimant stated
that he was ready to proceed, Tr. p.15. The claimant answered that he had a full
opportunity to produce evidence, Tr. p.22, although he then stated that the in
vestigation was not conducted fairly and impartially, Tr. p.22, 23. This un
certainty does not help the claimant.
The questions asked by the claimant's representative and the testimony offer
ed by both parties showed that they were familiar with the subject matter. The work
performed and the damage which occurred later were discussed by the witnesses for both
sides in great detail. Additional witnesses for either side could hardly have added
more information or knowledge than was presented. It is basic to the presentation
of proof that it is not the quantity but the quality of the evidence which must be
considered. If the machinist on vacation had unusual or otherwise unobtainable
evidence to offer, that should have been made known before the hearing started.
First Division Award
19699
states the conclusion to be followed by reasonable Joe
people, in substance, that the claimant could not reasonably doubt what he was .
charged with having done wrong.
There is considerable controversy over the question of fault. Organization
representatives have argued the question at great length~and vehemently, demonstrat
ing complete familiarity with the work in question, including discussion at this
level. Nevertheless, fundamental policy is so well established that it cannot be
ignored. When called upon to review decisions of administrative agencies, the
Courts have consistently refused to upset the decisions if substantial evidence
has been produced to support the result. Substantial evidence does not require that
it'be by a preponderance of the evidence or beyond a reasonable doubt. This Board
has held this to be so in many cases, see Second Division Awards No.
6196, 3676, 440l,
4407, 5020;
and Third Division Award No.
15574.
We do not believe that it would violate the policy sated herein if we dis
agreed with the penalty imposed upon claimant as related to the discipline handed out
to the two other machinists. If they were also parties to the wrongdoing, as decided
by the Carrier, and if discipline is to be measured by degree, then the 30-day actual
suspension is excessive. Claimant's penalty should be reduced to 30 days deferred
suspension.
He
should be paid for lost time at the pro rata rate.
A W A R D
Claim disposed of in accordance with findings.
Form 1 Award No. 6362
page
3
Docket No.
61`,15
2-MP-MA-'72
NATIONAL RAILROAD ADJLJSTiEar BOARD
By Order of Second Division
Attest:
^ . ~t.~,
Executive Secretary
Dated at Chicago, Illinois, this 14th day of July, 1972.