(Advance copy. The usual printed copies will be sent later.)
Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No.
6572
SECOND DIVISION Docket No.
6506
2-MP-MA-'73
( International Association of Machinists and
( Aerospace Workers
Parties to Dispute:
( Missouri Pacific Railroad Company
Dispute: Claim of Employes : .
1, That the Missouri Pacific Railroad Company violated the controlling
.agreement, particularly Rules 26(a), and 52(a), and letter of
Understanding of May 1,
1940,
when they arbitrarily transferred the
work of installing steam generators in Power House located at Pike
Avenue Shop, North Little Rock, Arkansas, from the Machinist's-Craft
to Sheet Metal Workers' Craft.
2. That accordingly, the Missouri Pacific Railroad Company be ordered
to compensate Machinists L. B. Schultz and H. H. Haustein in the
amount of eight hours
(8')
each at punitive rate for July 27,
1971,
as they were available to perform this work coming within the classification of Machinists.
Statement:
The above question was submitted to the Second Division of the National
Railroad Adjustment Board by the above referred to organization in ex parte form,
hearing thereon was waived, and the Division is now in receipt of a request from
the employes that the case be withdrawn.
A W A R D
Claim dismissed.
NATIONAL RAILROAD
ADJUSTMENT
BOARD
By Order of Second Division.
Attest: Executive Secretary
Na~i~ual Railroad Adjustment Board
BY~
~°, ,y.
Rosemarie Brasch - Administrative Assistant
Dated at Chicago, Illinois, this 14th day of September,
1973.
t