,w.
Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 677+
SECOND DIVISION Docket No. 6590
The Second Division consisted of the regular members and in
addition Referee Irving R. Shapiro when award was rendered.
a
( Sheet Metal Workers' International
( Association
Parties to Dispute:
( Louisville and Nashville Railroad Company
Dispute: Claim of Employes:
1. That the Louisville and Nashville Railroad Company violated
the controlling Agreement, particularly Rule 87, on December
24, 1970, when they improperly assigned Electricians the duty
of installing high and low copper freon pipes to air
conditioning unit, Second Floor, South Louisville Store
Department, Louisville, 'Kentucky.
2. That accordingly the Louisville and Nashville Railroad Company
be ordered to compensate Sheet Metal Workers J. Bowles and
T. E. Greenwell, Jr., for eight
(8)
hours each at the pro
~ rata rate of pay for such violation.
_ ,
Findings:
The Second Division of the Adjustment Board, upon the whole record
and all the evidence, finds that:
The carrier or carriers and the employe or employes involved in
this dispute are respectively carrier and employe within the meaning
' of the Railway Labor Act as approved June 21, 193+.
I
This Division of the Adjustment Board has jurisdiction over the
dispute involved herein.
Parties to said dispute were given due notice of hearing thereon.
This claim arose out of the assignment by the Carrier of two
electricians to perform work which Petitioner contends was work accruing
to mechanics of the Sheet Metal Workers' Craft pursuant to the provisions
of the Classification of Work Rule 87 of the controlling agreement
between the Parties.
It is uncontroverted that on and before December 24, 1970, Carrier
undertook "the modernizing of existing buildings by the installation of
a centralized Trane combination heater and air-conditioning system. fin
installation of such magnitude required the manufacture of air ducts
for controlling the flow of air, both hot and cold to all parts of the
L--- building. To the heating section of the unit it was necessary that gas
1
Illoe
Form 1 Award No. 677+
i w
Page 2 Docket No. 6590
2-L&N-SM-'74
and hot and cold water pipes be installed which involved the cutting,
threading, applying of all valves, couplings, controls, etc. Both
black and galvanized pipe were used.
"The above work was correctly assigned to and was performed by
the Sheet Metal Workers.
"The Trane air-conditioning section to obtain maximum efficiency
required that the cooling radiator be placed outside of the building
which is some 40 ft. from the compressor itself. The B&B gang fastened
the cooling radiator outside of the building and drilled necessary holes
in the building for"
...
"workers to connect the high and low copper
pipes to it from the compressor. Following the print of instructions
for proper application of the unit furnished by Mr. Ballard to the
Sheet Metal Workers
...
the Sheet Metal Workers obtained all necessary
copper pipe, fittings and torch to be used to easy flow various joints
and connections to the copper pipe. However, upon starting to work
on the 5/80D and 7/80D type L copper freon gas pipes, Mr. Ballard said
Mr. C. D. Medor had given this work to the Electricians and for the
Sheet Metal Workers to return to the shops. They were gold to leave
their torch, copper pipe and fittings there for the other craft to use."
(The materials in quotation marks are taken from Petitioner's March 18,
1972 letter which is marked Exhibit "S" appended to the submissions
of both Petitioner and Carrier and is not contested as to its factual
content).
Carrier challenges this Board's authority to determine this dispute
herein. It sets forth that in accordance with long standing practice
e
on the property, Carrier honored the claims of the Electrician's Craft,
that this phase of the work rightfully must be assigned to mechanics
of that classification and that the conflict constitutes a jurisdictional
dispute, subject to processing in accordance with Appendix "A" of the
controlling agreement, relative to such matters, and that Petitioner
herein has not complied therewith and is therefore foreclosed from
having this claim considered by the Board on the merits and it should
be dismissed.
c
I
The Carrier having raised a third party's interest in the matter_
t
the Board, pursuant to Section
3,
First (j) of the Railway Labor Act
as Amended, gave due notice to the International Brotherhood of Electrical
Workers, via the Railway Employes' Department, A.F.L.-C.I.O. of the
claim herein, affording it the right to intercede in behalf of the
employes it represents. The Electrical Workers filed an ex-pane
submission, rebuttal submission to Petitioner's ex-parte submission and
appeared and argued at the hearing conducted by the Board in which
all Parties concerned participated.
l
Form 1 Award No.
677+
~'-_ Page
3
Docket No.
6590
2-I&N-SM-'
74
The threshhold issue to be resolved, is whether the Sheet Metal
Workers complied with its alleged contractual obligation to follow the
edicts of "Appendix 'A'" of the controlling agreement. This Board is
most cognizant of the rationale underlying the documents which are the
component parts of said Appendix. The controlling agreement is one
between Carrier and six unions representing various categories of
employes employed by it and falling under the generally accepted connotation of "shop crafts". In the nature of things, changes in method cf
operation, equipment used, techniques for maintenance and repair of
installations, facilities, rolling stock, etc., must take place as
Carriers seek to "keep up" with the times and endeavor to provide a
viable system of transportation. The Organizations, Parties to the
jointly entered into controlling agreement, determined to avoid
controversies concerning the performance of certain work which the
referred to changes brought about. Thus on July
13, 19+3,
the System
Federation composed of representatives of six Organizations representing
shop crafts covered by the controlling agreement -with this Carrier,
advised Carrier of the agreement they had reached to avoid controversy
and disruption of services stemming from disagreements as to which
craft shall perform certain work required by Carrier. The key portions
of said notice to Carrier, pertinent to the dispute before us, ready
" . no general chairman, or other officer, representative
or member of arty of the organizations signatory hereto, will
individually request management to take work from one craft
and give it to another craft.
. we will find a way to reach an agreement and settle
any disputes that may arise between any two crafts
' signatory hereto, involving jurisdiction of work, and
when such dispute has thus been settled, then request will
be presented to management for conference to negotiate the
.i
acceptance by management of the settlement thus made .
...
each craft shall perform the work which was generally
recognized as work belonging to that craft prior to the
introduction of any new processes, and that the introduction
of a new process does not give any craft the right to claim
- the exclusive use of a process or a tool in order to secure
for itself work which it did not formerly perform.
' In the event of arty disagreement between two or more crafts
as to the proper application of the above rule then the
i craft performing the work at the time of the change of the
process or tool shall continue to do the work until the
organizations involved have settled the dispute and
the System Federation signatory hereto has presented such
settlement to management, requested a conference and
J
negotiated an agreement for acceptance of such settlement
by management . ..."
1
1
low
Form 1 Award No.
677+
''Page
4
Docket No.
6590
2-L&N-SM-'
74
Carrier replied on August
9, 19+3:
"The Management appreciates the fact that it is your desire
e to settle these matters without controversy and the
Company was not going to have any trouble by reason of
jurisdictional disputes within your crafts, that you would
settle these matters between you .
...
I do not understand what there is about the matter that
you have asked that the Company enter into any kind of an
agreement. Naturally it will be our purpose to carry out
the agreement in all cases and will not be the purpose of
the Company to in any way infringe upon the rights of any
craft."
Under protest, the Sheet Metal Workers acceded to Carrier's
exhortations to meet with the Electrical Workers, with reference to
the work involved in the installing and connecting of copper tubing
necessary for freon gas to be transmitted between the cooling radiator
outside Carrier's Stores Department Building, Louisville, Kentucky, and
the compressor located within the structure. Representatives of the
Organizations undertook a joint study of the work involved, as appendix
"A" of the controlling agreement indicated they would. They could not
resolve their differences as to which craft was, pursuant to the
classification of work provisions of the controlling agreement as applied
on the property entitled to be assigned to the work involved. The
classification of work provisions of the controlling agreement as applied
on the property entitled to be assigned to the work involved. The
Electrical Workers' representative did make a compromise proposal to the
Sheet Metal Workers, the terms of which are only vaguely brought to our
attention. The Sheet Metal Workers did not'formally-or directly reply
to same. Instead, it moved its claim before this Board.
Carrier and the Electrical Workers aver that this failure on the
part of the Sheet Metal Workers left the so-called jurisdictional
dispute in an undetermined status and accordingly, may not be acted
upon by this Board. The submission of the claim by the Sheet Metal
Workers to this Board constituted a clear and definitive rejection
by that Organization of the referred to, although not specifically
placed before us, Electrical Workers proposal. It must be noted that,
even if the Sheet Metal Workers had agreed to said proferred compromise,
Carrier was not bound thereby, and could, pursuant to Appendix "A"
refuse to comply therewith. In its denial letter of April
8, 1971
(Carrier Exhibit "E") Carrier asserts that it was not a Party to and
never agreed to Memorandum of Understanding reached between the Sheet
Metal Workers International Association and the International Brotherhood
of Electrical Workers in June,
1959,
known as the, "Miami Agreement"
_, which may have a relationship to the dispute herein.
Form 1 Award No.
677
Page
5
Docket No.
6590
2-I&N-SM- ` 74
Where do we go from there? Appendix "A" makes no provision for
circumstances where an attempt by the Organizations to resolve an
alleged jurisdictional dispute fails. Absent such an agreement, the
impact of Appendix "A", a Carrier's refusal to be a party to and accede:
thereto, restores the normal procedures for processing a claim of noncompliance with a classification of work rule of the controlling
agreement, as held in Award
2898
of this Board. It most certainly is
available to Petitioner in the instant dispute. Clearly distinguishable
are Awards
27+7
through
2780
and
2931
through
2936,
in which this Board
remanded similar claims for further handling on the property where it
was firmly established that there was an agreement in accordance with
letters comparable to those set forth in Appendix "A" of the controlling
agreement between the Parties hereto. However, the Petitioners in those
cases did not fulfill the procedural steps called for in such letters
and the claims were referred back to the property in order that the
conditions precedent to this Board's consideration thereof could be
satisfied. The elements of those cases are not present here. The
purposes of the Railway Labor Act in establishing the National Railroad
Adjustment Board to bring to a conclusion disputes arising out of the
application and interpretation of Agreements between parties subject
thereto would be frustrated if we were to refuse to assume jurisdiction
and render a determination of the dispute underlying this claim.
II
The. application of the Classification of Work Rule
87
of the
controlling agreement was duly dealt with in Award
3770
involving a
dispute between the same Parties as are before us in this case. Although
in the situation then raised, Carrier had employed an outside contractor
to install air-conditioning equipment in one of its buildings, this
Board sustained a claim which charged that
"...
other than Sheet Metal
Workers were improperly used to perform the work of installing and
assembling all piping and pipe fittings in connection with the installation
of all air conditioning units and their appurtenances..." Therein is
clearly delineated the extent to which the Sheet Metal Workers'
Classification of Work Rule applied to newly installed air-conditioning
equipment. The fact that in the dispute before us employes of the
Carrier in another craft were employed to do the work which an outside
contractor was used to do in
1957
and
1958
does not change the tenor of
the precepts of Award
3770.
Nothing in the record before us warrants
finding that determination defective and it is therefore reaffirmed.
The practices alluded to with reference to maintaining, servicing, and
repair of air-conditioning units is not applicable to the installation
of new heating and air-conditioning equipment such as that which took
place in December,
1970
in Carrier's Stores Building in Louisville,
Kentucky. Rule
87,
as Award
3770
clearly held, requires the assignment
of all piping work from the cooling radiator to the compressor be made
to Sheet Metal Workers.
,.,!
Form 1 Award No.
677+
Page
6
Docket No.
6590
2-I&N-SM-'
74
III
There is serious controversy in the record as to the remedy for
the breach of the Agreement and there is insufficient evidence to enable
the Board to arrive at an appropriate conclusion thereon. We are
referring this aspect of the claim back to the Parties, without prejudice,
for their further efforts to resolve this, consistent with the holdings
of the Board relative to making employes whole for alleged damages
sustained through breach of an agreement.
A W A R D
Part 1 of Claim sustained.
Part 2 of Claim is remanded in accordance with the Findings.
NATIONAL RAILROAD
ADJUSTMENT
BOARD
By Order of Second Division
Attest: Executive Secretary
National Railroad Adjustment Board
.~
By
Ros marie Brasch - Administrative Assistant
Dated a Chicago, Illinois, this 21st day of October,
197+.
I
I
~.: --
~~.
j:=~.
~ U U r1
,p
J
CARRIER MEMBERS' DISSENT TO AWARDS c,774
, a
f ; S . 6 ^ ; 6 , o
;'"" , r
~ ; 78
(Referee Shapiro)
Carrier Members respectfully submit that these awards are invalid on jurisdictional grounds.
The author of these awards refuses to recognize and enforce clear agreement
provisions which all parties to this dispute frankly concede are binding upon them
and those provisions establish the usual manner for the handling of such claims.
The provisions read
".
. . no . . representative of organizations signatory hereto,
will individually request management to take work from one craft
and give it to another craft .
'·.
. , we will find a way to reach an agreement and settle any
dis,gutps that may arise between any two crafts signatory hereto,
involving Jurisdiction of work, and when such disvute has thus
settled, then request will be ,presented to management for
conference $,o negotiate the acceptance by management of the
settlement thus made." (Underlining added.)
We do not believe the parties could have found language that would have more
Nearly expressed an agreement absolutely prohibiting any of the signatory org,aniza-
has from individually presenting to Carrier a claim involving jurisdiction of work
4d another signatory organization. Furthermore, the record leaves no room whatever
to doubt the fact that these clear provisions are an agreement that binds all of the
parties to the instant dispute. Carrier and the Electricians both cite and rely on
them and the petitioning Sheet Metal Workers concede their existence, never question
their complete validity, never claim they have been complied with, but attempt to
avoid their effect in these particular cases by advancing the incredible argument
that these cases
do
not come under said agreement provisions because the piping work
involved is allegedly reserved to Sheet Metal Workers by their Classification of Work
Rule. The complete answer to this argument is that the parties had before them the
Classification of Work Rules when they agreed to said provisions, yet they saw fit to
establish no exception to their unconditional commitment.
These awards significantly do not adopt this absurd argument of the Sheet Metal
Workers. Rather, the author contrived objections of his own to the crystal clear
agreement, referring to the obligation of the parties thereunder as an "alleged
contractual obligation", citing the irrelevant fact that Carrier was not a party to
the "Miami Agreement" and concluding that "Appendix 'A' makes no provision for circumstances where an attempt by the Organizations to resolve an alleged jurisdictional
dispute fails." (Underlining added.)
In view of the confusion that is so abundantly apparent in these awards, we
wonder what is meant by this reference to an "alleged jurisdictional dispute";
therefore, we
will
avoid that terminology and speak in the clear, unambiguous and
w'·solute terms of the agreement provisions that are controlling. Those provisions
(~ that no signatory organization "will individually request management to take work
~uway frpm another craft" and that the signatory organizations
"will
find a way, to
reach an agreement and settle any dispute that may arise between any two craft's signatory hereto, involving the jurisdiction of work, and when such dispute has thus beer
Dissent to Awards
n??4, 6% "5, o"."6. OW?, 6J "3
Page 2
"set
tled, then request will be presented to management . . .t" Certainly, these claims
come under the ban of those provisions, and the author of these awards has simply
reW sed to recogniLe said provisions and give them their intended effect.
as
the Electricians point out in their third party submission, Section 3 Firs'ty;
of the Railway Labor Act provides that disputes cannot be brought to this Board until
they have been handled on the property in the usual manner; and the usual manner for
handlinga jurisdictional dispute of the type involved in these claims makes it mandatory that agreement be reached by the two organizations claiming the work before any
claim can be submitted to Carrier and further processed.
This Board has consistently and
without exception recognized that a rule of
procedure such as that quoted above rust be complied with as a condition precedent to
properly invoking the jurisdiction of this Board. In Award 28% which is cited in
Award 6774 as authority for assuming jurisdiction in the instant cases, the Board
expressly found that: "The said dispute was settled under the jurisdictional dispute
procedure of February 15, 1940 between the organizations by agreeing that the work
belonged to the Sheet Metal Workers." Certainly that award is no authority for assuming jurisdiction in the instant cases where no agreement was reached and it was the
petitioning organization that terminated the negotiations of the parties. See Awards
2747 through 2780 (Smith), _2931 through 2936 (Kiernan), 5789, 5793 (Coburn), 6759,
6763, 6765 Eischen).
The cited Eischen awards were released a few days after release of the proposals
in the instant cases and thus represent the latest expression of any Referee concerning the jurisdictional question presented in these cases. It
will
be observed that
the last Eischen award (6765) involved the same Petitioner, the same Carrier, and the
same agreement that are involved in these cases. This award correctly concludes:
~"de have often decided cases of the type presented herein and we
can see no justification for now deviating from that clear precedent.
See Awa-rds
2931, 2930, 5789
and
5793.
We cannot ig-nore valid and
leg
its
operstire agrsemer_ts entered into in good faith by the parties,
notwithstanding
subsequent changes
in alliances and allegiances. In
the instant case, sack an agreement contemplates the submission of such
disrute to attemvted mutual resolution among the Organizations involved
wi th conference negotiation with management for acceptance oz' such inter
-
Orgrn.izational settlement.
t
fi·Te find that the instant dispute is referrable -oroperly to the
resolution machinery established by An-pendix 4 of the agreement and is
prematurely before our Board for a tudication pursuant to the brovisivns
_of Section 3, First (i) of the Railway Labor Act, as amended, and Circular
'71o.
1 of the National Railroad Adjustment Board.
"Consistent with the foregoing,
_·we are without jurisdiction to decide
this claim on its merits. Accordingly, it will be dismissed without
prejudice. « (Underlining added.)
These claims also should have been dismissed for
lack of jurisdiction because they
have not been handled in the usual manner,