Form 1
Dis up te: Claim of Em lp oyes:
 
NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 6966
 
SECOND DIVISION Docket No. 6905-T
  
2-AT&SF-SMW-' 75
( Sheet Metal Workers' International Association
( A. F. L. - C. I. 0.
Parties to Dispute:
 
(
 
( The Atchison, Topeka 
and Santa 
Fe Railway Company
1. That 
Sheetmetal 
Worker 
B. A. Ashworth 
be additionally
compensated at his established rate in the amount of four
(4) Hours for work performed by others tha to Sheetmetal
Workers on Caboose No. 355 on date October 7, 1974 and
additionally compensated in the amount of four (4) Hours
at his established rate for work performed by others than
Sheetmetal Workers on Caboose No. 360 date October 3, 1974.
2. This, being a continuing claim, that the Claimant 
(Kr. 
B.
A. Ashworth) be additionally compensated in the amount of
four (4) hours at his established rate for each day Carrier
records show others than Sheetmetal Workers performed
sheetmetal workers work on other Cabooses.
Statement:
The above question was submitted to the Second Division of the
National Railroad Adjustment Board by the above referred to organization fn
ex pane form, hearing thereon was waived, and the Division is now in receipt
of a request from the employes that the case be withdrawn.
A W A R D
Claim dismissed.
Attest: Executive Secretary
 
National Railroad Adjustment Board
e
 
, OL-9~
By __ _
Ro rie Brasch - Administrative Assistant
Dated at Chicago, Illinois, this 
2nd 
day of T)ecember, 1975.
NATIONAL RAILROAD ADJUSTMENT BOARD
 
By Order of Second Division