-  Form 1 _ NATIONAL RAILROAD ADJUST14ENT BOARD Award No. 7004
   
SECOND DrJISION Docket No. 6913-T
   
2-L&N-td4-' 76
   
The Second Division consisted of the regular members and in
   
addition Referee David P. Trromey when award was rendered.
Parties to Dispute:
Dispute: Claim of Employes:
International 
Association of 
Machinists and
 
Aerospace Workers
Louisville and Nashville Railroad Company
(a) That the Carrier violated the Controlling Agreement (farming
out of work) when on April 
24, 
1974 an outside contractor
(Esco 
Company) raised into place a 60' hood used for ventilation
in the 
new 
building on Track #9 at the South Louisville Shops,
Louisville, Kentucky.
(b) That the Carrier be required to pay the top three machinists
on the 
Rigging 
Gang Miscellaneous Overtime Board eight (8)
he:zrs each at penalty rate, and pay the top man on the Fro=cn
Group Miscellaneous 
Ovcxtime Board eight (8) hours of penalty
rate for Pettibone Operator.
`JStatement.:
 
The above question was 
submitted 
to the Second Division of the National
Railroad Adjustment Board by the above referred to organization in ex rte form,
hearing thereon was 
waived, 
and the Division is now in receipt of a request from
the employer t the case be withdrawn.
A WA R D
Claim dismissed.
Attest: Executive Secretary
 
National Railroad Adjustment Board
NATIONAL RAILROAD ADJUSTMENT 
BOARD
 
By Order of Second Division
Ros~marie Brasch - Administrative Assistant
Dated flat Chicago, - Il linois, this 10th day of February, 1976.