Form 1
NATIONAL RAILROf ) ADJUSTMENT BOARD
SECOND i*V ISION
( Sheet Metal Workers' International Association
( A. F. of L. - C. I. 0.
parties to Dispute:
(
( The Texas and Pacific Railway Company
Dispute: Claim of Employes:
Award No. 7043
Docket No. 6967-T
2-T&P-SMW-'76
1. That the Texas and Pacific Railway Company violated the controlling
Agreement, particularly Rule 65 a t Fort Worth, Texas on March 5,
1974 when they improperly assigned Carmen Perkins and Woodall the
duties of removing pipes from old commode and wash basin and
applying new pipes to Microphor commode and wash basin by cutting,
bending and fitting water and air lines of copper and galvanized
pipes also applying waste disposal lines on Caboose No. 13103.
2. That accordingly the Texas and Pacific Railway Company be ordered
to compensate Sheet Metal Workers J. H. Harrison and J. F. Raney
sixteen (16) hours each at the pro rata rate of pay for such
violation.
Statement:
The above question was submitted to the Second Division of the
National Railroad Adjustment Board by the above referred to organization in
ex pane form, hearing thereon was waived, and the Division is now in receipt
of a request from the employes that the case be withdrawn.
A W A R D
Claim dismissed.
Attest: Executive Secretary
National Railroad Adjustment Board
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Second Division
By
o~emarie Brasch - Administrafive Assistant
Dated at Chicago, Illinois, this 20th day of April, 1976.