Form 1 NATIONAL RAILROAD
ADJUSTMENT
BOARD
Award No. 7074
SECOND DIVISION Docket No. 6901
2-B&O-CM-'76
The Second Division consisted of the regular members and in
addition Referee Louis Norris when award was rendered.
( System Federation No. 4, Railway Employes'
( Department, A. F. of L. - C. I. 0.
Parties to Dispute: ( (Carmen)
( The Baltimore and Ohio Railroad Company
Dispute: Claim of Employes:
1. That the Carrier violated the provisions of the controlling
Agreement by bringing in an outside concern to perform wrecking
within the yard limits at Willard., Ohio.
2. That the Carrier be ordered to compensate Carmen V. Miller,
John Polocheck,
R. 0.
Morey, C. G. Coffmans John Bores, C. L.
Biettner, C. D. Sage, Harold Gates, J. C. Henery, J. Andersac,
and Assistant wreckmaster, li. C. Puckett for 13 hours and 20
minutes, time and one-half rate and wreckmaster
R.
E. Sage in
the amount of 4 hours and 5 minutes a t time and one-half rate.
Findings:
The Second Division of the Adjustment Board, upon the whole record
and all the evidence, finds that:
The carrier or carriers and the employe or employes involved in this
dispute are respectively carrier and employe within the meaning of the
Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the
dispute involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
The basic facts involved in this dispute are not seriously in issue.
On September 4, 1973, at approximately 12:40 p.m., a derailment occurred at
the eastbound receiving yard a t Carrier's facilities located a t Willard., Ohio.
This derailment involved ten cars and tope up 880 feet of track of the eastbound
main, 300 feet of No. 1 yard track along with the yard lead, and about 100 feet
of the No. 2 yard track.
The regularly assigned Willard wrecking outfit and crew were called to
this derailment at 1:00 p.m. on September 4 and relieved of duty at 12:00
midnight on September 4. While the work was in progress it was determined that
some of the derailed cars were not accessible to the wreck derrick and that
off-track equipment would be needed. Accordingly, Carrier called the Hulcher
Company, an outside organization, at 2:45 p.m. on September 4. The Hulcher Company's
Form 1 Award No. 7074
Page 2 Docket No. 6901
2-B&O-CM-t76
equipment and 12-man crew arrived at the scene at 5:30.p.m., commenced
work at 6:00 p.m., and continued the rerailing work, using their off-track
equipment, until 4:05 a.m. on September 5, at which time the work was
completed.
Petitioner contends that Carrier violated the controlling Agreement,
particularly Rule 142, when it called in an outside concern (Hulcher Company)
to perform wrecking and rerailing services within yard limits. Demand is
made in the claim for compensation to specific Carmen who were available to
perform the work here in dispute.
Rule 142 reads as follows:
"When wrecking-crews are called for wrecks or
derailments outside of yard limits, a sufficient
number of the regularly assigned crew will accompany
the outfit. For wrecks or derailments within yard
limits, sufficient carmen will be called to perform
the work."
It is not disputed that initially Rule 142 was complied with when the
Willard wrecking outfit and regularly assigned wrecking crew were called to
the derailment. Petitioner contends, however, that wrecking and rerailing
work within yard limits belongs exclusively to Carmen by agreement and by
"historical practice", and, accordingly, that the use of the Hulcher equipment:
and crew violated the Agreement. Moreover, that Carrier had ample time (5
hours) before arrival of the I-Iulcher crew to rebuild the torn out track so that
the Willard wreck crew could have completed the work, but that Carrier made
little effort to do so.
Carrier responds that the Willard crew did in fact rerail those cars
within reach of the regular rail-operating outfit, but that off-track equipment, which Carrier did not possess, was necessary to complete the rera fling
work. This necessitated calling in the Hulcher Company which did possess off-track equipment. Additionally, Carrier asserts that an emergency situation
existed in that some 1280 feet of track was torn up, which included the eastbound main, the yard lead and No. 1 and No. 2 yard tracks; that an additional
eight to ten hours work was necessary to clear up the derailment; that extensive
delay would have caused blocking of the westbound main and disruption of other
operations; and, accordingly, that it acted within its managerial prerogatives,
in deciding to clear the derailment as expeditiously as possible by calling in
the Hulcher Company to complete the work.
Turning first to Petitioner's contention of exclusivity, although prior
Awards are not in complete agreement, the clear weight of authority supports the
principle that under Rule 142 (or similar Rules) Carmen do not have the exclusivF
right to do the work of rerailing cars unless a wrecking outfit and crew are
called or required to do the work. These findings have been made as to wrecks
occurring within and outside of yard limits.
Form 1 Award No. 7074
rage 3 Docket No.
6901
2-B8r0-CM-' 76
See Awards
2343, 3257, 4337, 4901,-4931, 5306,.5621, 5860, 6030,
6454
and
6703.
Consequently, although both principals devote a goodly portion of
their Submissions to discussion of whether the wreck occurred "within" or
"outside oft yard limits, we do not consider this issue as paramount in this
dispute in view of the above precedents and for reasons detailed hereafter.
Petitioner contends, further, that the disputed work belongs to Carmen
exclusively on the basis of "historical practice". However, no factual
evidence is offered to substantiate such assertion, which thus becomes merely
conclusory in impact. This Board has held repeatedly that mere conclusory
allegations are no substitute for factual evidence.
See, for example, Award 1760; Third Division Awards
8065
and
9609;
and
Fou.;th Division Award
1486,
among others.
In essence, Rule
142
requires that "sufficient Carmen will be called
to perform the work". Initially, this requisite was complied with. The
question remains, however, whether Carrier was justified, under the facts and
circumstances of this case, in calling in outside forces to complete the work.
The answer to this question hinges upon two issues. Firstly, whether an
emergency situation did in fact exist; and, secondly, whether Carrier acted
reasonably and logically and did not abuse its managerial prerogatives.
On the second proposition, there is no evidence in this record that
Carrier's determination to call in the Hulcher outfit and crew was in any
sense unreasonable or illogical. Moreover, if an emergency situation did in
fact exist, then Carrier acted properly and within its management responsibilities and prerogatives. This brings us to the paramount issue which confronts
us here - the alleged emergency.
This Board has held that a minor delay and the fact that outside
forces may expedite the work somewhat are not in themselves sufficient to
constitute an emergency. Thus, in Award 5191, the saving of "three hours time"
was held to be without merit; and in Award
4600
Carrier's desire to avoid delay
to a single passenger train did not make "time of the essence" or constitute
an emergency. Similarly, in Award 6703, Carrier failed to sustain its burden
of proving that its equipment was unsuited to complete the rera filing operations.
The fa ctual situation in this case is directly to the contrary.
Obviously, the situation in each case is pregnant with its own peculiar
facts and circumstances, and our determination of the applicability of the
emergency concept must be based on particular facts. The facts in this case
are that extensive track damage existed
(1280
feet of track having been torn up)
affecting the eastbound and westbound mains, the yard lead, and No. 1 and No. 2
yard tracks; that Carrier's equipment was inadequate to complete the rerailing
and that off-track equipment was needed, which Carrier did not possess; that
extensive delay and disruption of operations would result had Carrier attempted
to use its own equipment and forces to complete the work, assuming that this
could have been done
Form 1 Award No. 7074
Page 4 Docket No. 6901
2-B&O-CM-t76
In these circumstances, we are compelled to the conclusion that
an emergency did in fact exist, and that Carrier acted reasonably and
logically, and did not abuse its managerial prerogatives in calling in
outside forces possessed with the required off-track equipment to complete
the rerailing operations.
The following quote from Award 4581 is particularly applicable here:
"Much of the submissions of the parties hereto is
centered around the necessity of Carrier using
private equipment. The record is sufficiently
clear to convince us that Carrier was making full
use of its own available equipment and its decision
that an off-track crane such as it hired from the
Higgins Company was also necessary to the proper
handling of the derailment will not be disturbed
by us under these circumstances."
Similarly, in Award 6490 we held that the emergency concept will be
deemed applicable "primarily because the possibility of emergency is inherent
in the factual statement". We stated further:
"There is no doubt that min line blockade
and urgent movement of trains are emergency
situations but as in all emergencies judgment
is required to accomplish the necessary result."
(Emphasis added).
We conclude and find that "main line blockage and urgent movement of
trains" were factors involved in this case., and that Carrier acted properly
in exercising its judgment "to accomplish the necessary result". In short,
that an emergency did exist, and that Carrier was warranted in attempting
to clear the derailment as expeditiously as possible.
We point out, further, that the fact that the claim was sustained in
Award 6490 is not contrary to our findings here. In that case the IIulcher
crew and equipment arrived at the wreck site at 9:3Q p.m. on the day of the
wreck, but did not start operations until 5:00 a.m. the next morning, seven
and one-half hours later - sufficient time for Carrier to. have brought its
own 75 ton derrick into play. This created a substantial doubt as to the
validity of the claimed emergency.
In the case before us, the Hulcher crew and equipment arrived at the
scene at 5:30 p.m. and started work one half hour later. Additionally, the
necessity for use of off-track equipment was a further controlling factor. The
two situations, therefore, are clearly distinguishable.
Form 1
Page 5
Award No. 7074
Docket No. 6901
2-B&O-CM-' 76
We quote, finally, from Award 6582:
"In the case before us, there is evidence that
an emergency existed, there is no evidence that
the outside forces performed any work at the site
after the emergency ceased to exist and there is
no evidence that Carrier abused its managerial
prerogatives under all the circumstances. In view
of the foregoing, we find that there has been no
violation of the Agreement."
We so find in this case. Accordingly, based on the entire record and
controlling authority, we are compelled to deny the claim.
Finally, Carrier raises the issue "that Claimants Puckett and Sage
are Supervisors represented by the Foremen and Supervisors Agreement and,, as
such, the Second Division does not have jurisdiction to handle their claims."
Petitioner vigorously contests this issue, contending that these employees are
dues paying members of the Carmen's Organization; that they are part of the
original claim and should so remain; and, finally, that this issue constitutes
inadmissible "new matter", not having been raised during the processing of
this claim on the property.
In any event, in view of our findings and conclusions on the merits,
we deem it unnecessary to resolve this issue and, accordingly, we make no
determination thereof negatively or affirmatively.
A WA R D
Claim denied.
Attest: Executive Secretary
National Railroad Adjustment Board
BY.
Ro~semarie Brasch - Administrative Assistant
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Second Division
Dated at Chicago, Illinois, this 22nd day of June, 1976.