Form 1 NATIONAL .RA:LLt;OAD AhJu STMENT BOARD Award No.
7106
'
-),~ L
Docket No. 6854-T
-V'SION
2-MP-EW-'76
The Second Division con>isted of the regular members and in
addition Re.fexee.?:avid F., Twomey when award was rendered.
( System Federation No. 2, Railway Employes'
( Depax'tmeut, A. F. of L. - C. I. 0.
Parties to Dispute: ( (Electrical Workers)
(
( Missouri Pacific Railroad Company
Dispute: Claim of Employes:
1. That the Missouri Pacific Railroad Company violated the current
agreement when they assigned Signal Maintainers Jenkins, Larue,
Sturdevant and Herd to perform work within the scope of the
Electrical Craft.
2. That accordingly, the Missouri Pacific Railroad Company be
ordered to compensate Telephone Maintainer J. C. Ballard in the
amount of seventy three hours
(73') at
the punitive rate fox
August
13, 1973
and through the week thereof.
Findings:
The Second Division of the Adjustment Board, upon the whole record and
all the evidence, finds that:
The carrier ox carriers and the employe or employes involved in this
dispute are respectively carrier and employe within the meaning of the
Railway Labor Act as approved June 21,
193+.
This Division of the Adjustment Board has jurisdiction aver the dispute
involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
The Claimant, Telephone Maintainer (IBEW) J. C. Ballard, was assigned
by the Carrier to change over phone drops from the former dispatcher's line
to the Mobil Pipeline's wires. This meant disconnecting the wires leading
to each telephone located between Little Rock and Cordon from the former
dispatcher's line and connecting the wires to the Mobil Pipeline wires, which,
were to become the new dispatcher's circuit. (Carrier's Submission, p.
3)·
Sometime during the week of August
13, 1973,
the carrier assigned a portion
of this work of changing the telephone drops, initially assigned to the
Claimant, to Signal Maintainers, represented by the Brotherhood of Railroad
Signalmen, having the Signal Maintainers change the drops at the phone
booths within their territory that had not already been changed by Telephone
Maintainer Ballard (Carrier's Submission, p.
8).
The record shows that the
Carrier was willing to depend on one pair of wires during the week of
August
13, 1973,
but was not willing to rely on this one pair of wires over
Form 1 Award No.
7106
page 2 Docket No.
685+-T
2-MP-Ew-'76
the week-end August 18 and 19, 19(3, because of the delays inherent in
calling employes out to correct; difficulties should such arise during this
weekend period.
The Organization contends that the failure to allow the Claimant
Telephone Maintainer to complete the changeover was in violation of Rule
107(a) Classification of Work.---Electrical Workers.
The Carrier cona.ends that the work in question was not exclusively
Telephone Maintainers' work; that the changeover had to be completed and be
in service by the weekend; that no other
Telephone Maintainers
were available
to assist Claimant; and that since the
Claimant
is paid a monthly rate for
all service performed the first five days of the work week, the Claimant
would not have been entitled to additional compensation if required to work
sufficient hours during the week.to change all of the drops.
We find that the work in question is covered under Rule 107(a) which
states in pertinent part:
"Electricians' work
...
shall include electrical wiring,
maintaining, repairing
...
telephone equipment on the
Western and Southern Districts only
...."
The Carrier, indeed, initially properly assigned the work to the Claimant.
During the week of August
13,
however, the Carrier's supervision at Little
Rock determined that the Claimant would-not be able to change all the drops
by the *eekend and then assigned Signal Maintainers
so
that the Mobil line
would be in sex-vice over the weekend. (Mr. 0. B. Sayers' letter of May
6,
1g74).
Rule 107, itself, does not contain any exception under which the
Carrier can take the work of one craft and assign it to another. The Carrier
has its managerial prerogative in the assignment of work where an emergency
exists. The burden of proof is on the Carrier to demonstrate the existence
of an emergency, however, and, certainly in the case before us,
no
emergency
was ever alleged ox proven. The Carrier's need to have the second pair of
wires available fox the weekend was, as set out above, relating to the
difficulties inherent in calling out employes to correct difficulties should
such arise. Such is not an emergency situation. (See also Employes'
Rebuttal, p. 2).
The Organization and the Carrier present conflicting assertions as to
whether other Telephone Maintainers were available to help the
Claimant.
Relating narrowly to the assertions in the instant case, where no contractual
exception exists ox where no emergency is demonstrated, it is no defense fox
having transferred work of one craft to another to contend that the seven
other Telephone Maintainers were not available to work on the project because
of other assignments.
Concerning the Carrier's contention that Claimant would not have been
entitled to additional compensation if he was required to work sufficient
hours during the week of August
13, 1973;
to change all of the telephone
Form 1
Page 3
Award No,
7106
Docket No. 685+-T
2-MP-EW-'76
drops, since the Claimant is paid a monthly rate. The Carrier concedes that
it would have been impossible for the Claimant to finish the work by the
17th, (Carrier's Submission, p.
9).
Indeed, if the Signal Maintainers
required 73 hours to do the work. during the week of the 13th, then the Claimant
could not have, by himself, completed the job within a week. (The Carrier's
own evidence shows, contrary to the Carrier's contention that the work was
planned fox the week of August 13 and had to be completed by the weekend of
August
18
and 19, that Claimant Ballard~worked on the changeover assignment
a total of
88
hours from August 3 to August 23,
1973,
(See Carrier's
Submission, p.
4) ) .
In the instant case other Telephone Maintainers would have been required
if the job were to be started and completed within the week of August 13
through 17. The work irk question was clearly Telephone Maintainers' work and
it is the Carrier's obligation to keep available sufficient employee of a
craft so that the work granted exclusively to that craft by the Agreement
can be completed by the members of the
craft.
When the work 'in question
was wrongfully assigned to Signal M4intainers, the Telephone Maintainers
of the Electricians' Craft lost work they were contractually entitled to.
It is appropriate that there be a remedy for the work lost;. and that it be
paid to the Claimant.
While the Carrier contends in its Submission, p. 5, that 73 hours were
not spent changing telephone drops by the Signal Maintainers, we find that
such was never argued on the property and is thus not properly before us.
We.shall sustain the claim at the straight time rate.
Sustained as per findings.
Attest: Executive Secretary
National Railroad Adjustment Board
NATIONAL RAILROAD
ADJUSTMENT
BOARD
By Order of Second Division
;emaxie Brasch - Administrative Assistant
Dated at Chicago, Illinois, this 3rd day of July,
1976.