Form 1

NATIONAL RAILROAD ADJUSTMENT BOARD

SECOND DIVISION


Award No. 7175
Docket No. 7108
2-P&BR-CM '76

The Second Division consisted of the regular members and in addition Referee Nicholas If. Zumas when award was rendered.

Parties to Dispute:

Dispute: Claim of Emp?oyes:

System Federation No. 4
Railway Employes; Department
A.F. of L. - C.I.O. - Carmen

Patapsco & Back Rivers Railroad Company





Statement:

The above question was submitted to the Second Division of the National Railroad Adjustment Board by the above referred to organization in ex pane form, hearing thereon was waived, and the Division is now in receipt of a request from the employes that the case be withdrawn.

A 14 A R D

Claim dismissed.

Attest: Executive Secretary
National Railroad Adjustment Board

By~L1 .,-. Q-i2~/
Rosemarie Brasch - Administrative ssi.stant

Dated at Chicago, Illinois, this 23rd day of November, 1976.

NATIONAL RAILROAD ADJUSTMENT BOARD

By Order of Second Division