Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 7246
SECOND DIVISION Docket No. 7032
2-SCL-CM-t77





Parties to Dispute: ( (C armen)



Dispute: Claim of Employes:





Findings:

The Second Division of the Adjustment Board, upon the-whole record and all the evidence, finds that:

The carrier or carriers and the employe or employes involved in this dispute are respectively carrier and employe within the meaning of the Railway Labor Act as approved June 21, 1934.

This Division of the AdJustment Board has jurisdiction over the dispute involved herein.



The issue to be,decided in this docket is whether the work performed by Claimant on his first rest day, November 23, 1974, came within the exception contained in Article V of the National Agreement of April 24, 1970, i.e. was the work performed "emergency work". There is no dispute with respect to the Claimant workJ:ng all the hours of his assignment in the work week. Article V of the National Agreement of April 24., 1970, provides for the payment of double the basic straight time rate for work performed on the second rest day of an employee's work week provided he worked all the hours of his assignment in that work week and worked on his first rest day with the following exception:




Form 1 Award No. 72 46
Page 2 Docket No. 7032
2-SCZ-CM-'77

The claim is for an additional four (4) hours pay at the pro rata rate for service on Claimant's second rest day on the grounds that the service performed on the first rest day was not "emergency work" and therefore the exception in Article V does not apply.

Petitioner agrees that there is no dispute with Carrier (page 1 of Employees Rebuttal) as to the work performed by Claimant on his first rest day. Claimant retailed a loaded car at Durand, Georgia; then went to Fields, Georgia to change a dExmged wheel on a car loaded with gravel; then to Bineville, Georgia to change a damaged wheel on a car loaded with limestone. Claimant also performed service at other locations. The record shows that the derailed and damaged cars were located in pass and/or spur tracks in single track territory and, a~s asserted by the Carrier, if not promptly repaired would have seriously affected the Carrier's operation. It was for this reason that the Carrier deemed the work to be of an emergency nature.

Petitioner premised his argument on the fact that the damaged cars were not blocking the main line and that, therefore, no emergency existed. Petitioner cited Third Division Award No. 4354, among others, as defining what constituted an emergeicy, to grit:



Petitioner also cited Third Division Award No. 2040 which stated in part:



Also cited by Petitioner was Second Division Award No. 5484, regarding the concept of burden of proof, as follows:



What is the competent evidence in the subject case? There is no disagreement between the partf_es to the fact that the damaged cars (presumedby logic to be inoperative) which were repaired by Claimant-such service being the reason for the Call-were in passing and/or spur tracks, were blocking said tracks, and tha,; said tracks were located in single track territory. Under these circumstances the Carrier determined that if the
Form 1 Page 3

Award No. 7246
Docket No. 7032
2-SCL-CM-177

needed repairs were not promptly made its operations would have been seriously affected, a decision that could only be made by the Carrier. In this situation one could hardy successfully argue that in order to determine the existence of an emergency a carrier would have to wait until its operations were actually impaired through not having had the needed work performed. To have done so would conceivably have exposed the Carrier to the defense of charges of a greater magnitude than are herein present! Having determined that the subject work could riot b e postponed and thus be performed by regularly assigned forces the: Carrier was obligated, by applicable provisions in the Agreement, to pay a penalty rate to the Claimant and this was done.

We find that, in this particular case, the Carrier met the burden of proof in asserting the existence of an emergency - the situation was "unusual rather than usual; ,.. extraordinary rather than ... ordinary." Therefore, the referrenced exception in Article V of the National Agreement of April 24, 1970, applies and we will deny the claim.

A W A R D

Claim denied.

Attest: Executive Secretary
National Railroad Adjustment Board

NATIONAL RAILROAD ADJUSTMEr1T BOARD

By Order of Second Division


;osemarie Brasch - Administrative Assistant

Dated at Chicago, Illinois, this 11th day of March, 1977.