Form 1 NATIONAL
RAILROAD ADJUSTMENT BOARD Award No.
71+36
SECOND DIVISION Docket No.
72+0
2-MP-CM-'78
The Second Division consisted of the regular members and in
addition Referee David P. Twomey when award was rendered.
( System Federation No. 2, Railway Employes'
( Department, A. F. of L. - C. I. 0.
Parties to Dispute: ( (Carmen)
(
( Missouri Pacific Railroad Company
Dispute: Claim of Employes:
1. That under the current agreement the Missouri Pacific Railroad
Company improperly assigned other than Carmen (wrecking crew
members) to assist and complete clearing up a derailment at
Spadra, Arkansas, beginning January
12,
1875.
That accordingly, the Missouri Pacific Railroad Company be
required to compensate wrecking crew members W. W. Wilson, M. T.
Linz, P A. Piechoski, M. H. Me Gary, J. D. Cantrell, H. E. Ison,
C V. Kita, L. W. Wise and L. S. Johns ninety (90) hours each at
pro rata rates.
Findings:
The Second Division of the Adjustment Board, upon the whole record and
all the evidence, finds that:
The carrier or carriers and the employe or employes involved in this
dispute are respectively carrier and employe within the meaning of the
Railway Labor Act as approved June 21, 193+.
This Division of the Adjustment Board has jurisdiction over the dispute
involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
The North Little Rock Wrecker and Crew was called for a derailment at
Spadra, Arkansas at 12:10 P. M., January 10,
1975.
The Wrecker and Crew
worked from
7:15
P. M., January 10,
1975
until 11:x+0 A.M., January 11,
1975,
clearing the main line. The Carrier also contracted for the services of the
Hulcher Company, whose equipment and crews arrived at the derailment and began
work at
8:x+5
P. M, on January 10,
1975.
The Carrier released its own Wrecker
and Crew to return to North Little Rock for standby duty to protect against
possible disruption of service; and kept on the outside contractor's
equipment and forces from January 11,,
1975
through January
16, 1975.
These
forces worked eight hours a day on the duties in question.
Form 1 Award No.
71+36
Page 2 Docket No. 72+0
2-MP-CM-'78
The Hulcher equipment used were two bulldozers with side booms, one
front-end loader and one heavy D-8 Caterpillar tractor all equipped with
winches. The Organization contends, and it is not denied, that Hulcher's
equipment replaced the Carrier's Wrecker crane in performing the rest of the
work of clearing the derailment. In Award No. x+835, involving the same
parties to this Agreement, we held that two draglines used in lieu of the
wrecking derrick to handle a derailment outside yard limits was a contract
violation. We find in the instant case that the Carrier violated Rule 119(a)
and Rule 120 when it utilized the equipment and personnel of an outside
contractor in lieu of its own wrecking crane and crew to clear up the
derailment at Spadra, for that period of time after the main line was opened
and the emergency conditions of the main line blockage had ceased.
The fact that the Coffeyville, Kansas Wrecker was out of service and the
Kansas City, Missouri Wrecker was in service cannot serve as a justification
for this contractual violation.
Under the narrow circumstances of this case the Claimants are entitled
to b e made whole for the wage loss, if any, resulting from this contract
violation. The Organization seeks 90 hours pay at pro rata rates; a claim
for 90 hours is not supported by the record, and is rejected. The Carrier
contends that had the Wrecking Crew been retained at the derailment site and
worked the same eight-hour days as the Hulchex crews, they would not have
earned more than they were actually compensated for this period.
We accept the Carrier's statements concerning the-total ntunber of hours
of work involved, since the record does not disclose anything to the contrary.
However, the test is not how the Hulcher Company and the Carrier may choose
to assign these outside forces, but rather how the Carrier would have assigned
its own forces, had the contract not been violated. After a main line is
opened, Carrier would still have the pressure to complete the work of clearing
up the derailment, in order to return the Wrecker to its home station to
protect against other possible disruption of service. The question then is,
would the Carrier have employed 8 hour per day assignments? The Carrier is
ordered to examine its records fox the three preceeding major derailments
(four days work or longer) prior to January 10, 1975, involving the North
Little Rock Wrecker; and to ascertain the average work day of the Wrecking
Crew for dates after the main lines were cleared, not utilizing the partial
work dates, if any, of the final work day at the derailment sites in computing
this average figure. Based on the average work day established by the above
procedures, each Claimant is entitled to be paid what he would have earned,
had the Wrecking Crew been allowed to complete the work in question, less what
he was paid for that specific period of time.
Form 1
Page
3
Award No.
7+36
bocket No.
72+0
2-MP-CM-'
7$
A W A
R D
Claim sustained as set forth in Findings.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Second Division
Attest: Executive Secretary
National Railroad Adjustment Board
By /
os arie Brasch - Administrative Assistant
Dated at Chicago, Illinois, this 6th day of January,
1978.
..