Form 1 NATIONAL
RAILROAD ADJUSTMENT
BOARD Award No. 7504
SECOND DIVISION Docket No. 7377
2-KCT-EW-'78
The Second Division consisted of the regular members and in
addition Referee Herbert L. Marx, Jr. when award was rendered.
( System Federation No. 3, Railway Employes'
( Department, A. F. of L. - C. I. 0.
Parties to Dispute: ( (Electrical Workers)
(
( Kansas City Terminal Railway Company
Dispute: Claim of Employes:
1. That the Kansas City Terminal Railway Company violated Rules 19,
20, 21 and 67 of the July 1, 1936 controlling agreement; Article
III of the September 25,
1964
Agreement when Assistant General
Foreman Edwards assigned himself to perform electricians' work
on April 23, 1975, thus, depriving Electrician C. W. Connor of
his contractual rights to said work at Kansas City, Missouri.
2. That accordingly, Carrier b e ordered to compensate Electrician
C. W. Connor eight hours (8') at the time and one-half rate for
April 23, 1975.
3.
In addition to the money amounts claimed, herein, Carrier be
ordered to pay interest on the principal amount claimed, computed
at the rate of
6%
per annum and compounded annually from the
anniversary date of this claim.
Findings:
The Second Division of the Adjustment Board, upon the whole record and
all the evidence, finds that:
The carrier or carriers and the employe or employes involved in this
dispute are respectively carrier and employe within the meaning of the
Railway Labor Act as approved June 21, 1934.
This Division of the Adjustment Board has jurisdiction over the dispute:
involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
Claim involves work performed on installation of office heating and
air conditioning controls, including thermostat and transformer. There is
no dispute that Claimant, an Electrician, performed such work on April 22,
24, and 25, 1975, and that on April 23, 1975, a portion of the work was
performed by an Assistant General Foreman, not of Electrician seniority,
at a time when Claimant was assigned to work elsewhere.
Form 1 Award No.
7504
Page 2 - Docket No. 7377
2-KCT-EW-'78
The Board finds no question involved that the work was properly that
of the Electrician craft, with no entitlement for it to be performed by a
foreman. Article III - Assignment of Work - Use of Supervisors provides
in part:
"None but mechanics or apprentices regularly employed as
such shall do mechanics' work as per the special rules of
each craft except foremen at points where no mechanics
are employed."
Since mechanics are employed at the point in question, the prohibition
against foremen performing craft work is clear. Whether or not the
Claimant's work was faulty on April 22, or the Assistant General Foreman's
work on April 23 was faulty, are not relevant issues.
The Board finds that the work was improperly assigned, and the
Electrician's claim for the work is justified under the applicable rules.
The question is one of remedy. The fact that the Claimant was under pay
and at work at another location at the time the Foreman performed the work
on the heating and air conditioning controls is not sufficient to defeat
a claim for pay.
The work should have been assigned to an Electrician -- at a time to
be determined by the Carrier -- and was work denied to a craft employee.
To say that the claimant is not entitled to pay because, at a given moment,
he was under pay elsewhere would obviously give the Carrier a latitude of
work assignment not sanctioned by the rules.
The claim for pay at the punitive rate, however, is not warranted.
This Board cannot determine when the work would have been done, if performed.
by an Electrician rather than the Assistant General Foreman. Likewise, the
claim for interest is not granted, based on the reasoning expressed in a
long series of awards on this issue b y the Board.
Finally, there is the issue of the amount of time involved. The
Board will not dismiss this as a _de minimas matter. Not only is the amount
of time involved in dispute between the parties, but also involved would
be the time for the Electrician to come to and depart from the site of the
work from another work location.
The Board will deny the claim for eight hours' pay at the punitive
rate, but will award such pay on the pro rata basis to be determined on
the property by the organization and the Carrier as if the Claimant had
been assigned to perform the work done by the Assistant General Foreman.
The Organization argues that the claim should be granted in full based
on the consideration that the Carrier failed to deny the claim in proper
fashion at one point in the appeal .procedure. The Board finds the
Carrier's reply of February 10, 1976; of sufficient clarity that a denial
is clearly implied, even if not specifically stated as such.
Form 1 Award No.
7504
Page
3
Docket No.
7377
2-KCT-EW-'78
A W A R D
Claim No. 1 is sustained.
Claim No. 2 is sustained in part to the extent indicated i n the
Findings.
Claim No.
3
is denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Second Division
Attest: Executive Secretary
National Railroad Adjustment Board
By,e~·~·r ~ . ··t~!,. _
emarie Brasch - Administrative Assistant
Dated at Chicago, Illinois, this 14th day of April,
1978.