Form 1 NATIONAL RAILROAD ADJUSTMENT' BOARD Award No. 7 23
SECOND DIVISION Docket No.
703
2-CR-CM-'
78
The Second Division consisted of the regular members and in
addition Referee Walter C. Wallace when award was rendered.
(, System Federation No. 100, Railway Employes'
( Department, A. F of L. - C. I. 0.
Parties to Dispute: ( (Carmen)
( Consolidated Rail Corporation
Dispute: * Claim of Employes:
That within the meaning of the controlling agreement, particularly
Rules 11, 121, 124 and
125,
the Carrier improperly used employees
of a private company, and their equipment, in performing wrecking
service on September
6, 1975
at Hendlers, Pa.
That accordingly the Carrier compensate Arnold Cochi, Joseph E.
Geffert, John Stromick, Orlando J. Alexander, Leo Bentley, John
Sparduti, Clement Altieri, Robert Alexander and Doug Depew, members
of the Sayre wreck crew, eight
(8)
hours each at the time and one
half rate of pay plus the number of hours travel time to and from
Hendlers.
Findings:
The Second Division of the Adjustment Board, upon the whole record and
all the evidence, finds that:
The carrier or carriers and the employe or employes involved in this
dispute are respectively carrier and employe within the meaning of the
Railway Labor Act as approved June
21,
1934.
This Division of the Adjustment Board has jurisdiction over the dispute
involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
The facts are not in dispute. Carrier sustained a mainline derailment
on Wednesday, September 3, 1975. The regular assigned Sayre, Pennsylvania
Wreck Crew along with additional carmen from Coxton, Pennsylvania were called
out and they cleared the mainline on that date. They were then relieved and
ordered to return to their home stations leaving six cars for rerailment
which were riot blocking the mainline. Thereafter, on Saturday, September
6,
1975, carrier arranged for Hulcher Emergency Service, an outside contractor
along with carmen from Coxton to rerail the six cars and clean up the
derailment scene. The claim alleges violations of Rules 11, 121, 124- and
125
of the applicable agreement and seeks eight
(8)
hours pay, at time and
one half rate each, for nine designated members of the aforesaid wrecking
crew plus travel time to and from Hendlers, the wreck site.
Form 1 Award No. 7523
Page 2 Docket No.
7403
2-CR-CM-'78
Rule 11 provides the method of payment fox wrecking crews. Rule 121
describes the work classified to carmen and makes no reference to wrecking
crew. Our attention is directed primarily to Rules 124 and 125 with
particular reference to the latter rule which provides in full:
"Rule 125
When wrecking crews are called for wrecks or derailments,
.a sufficient number of the regularly assigned crew will
accompany the outfit.
This shall not be construed to prevent train crews from
rerailing cars or locomotives, when wrecker is not
required."
The opinions of this Board have held that this rule and those like it
do not establish exclusive jurisdiction in the carmen requiring the carrier
to call them out when a wreck occurs. In effect, the carrier is vested with
the managerial prerogative to call such crews or not. See Award 7157 (Marx).
That is not the issue here however. The Carrier did call out the Sayre
Wrecking Crew and utilized them for the duration of the emergency, that is,
to perform the work necessary to clear the mainline and then relieved them
utilizing an outside contractor and carmen from Coxton to complete the work
of rerailing and cleanup which was not of an emergency nature three days
later.
The cases cited by the Carrier that emphasize the non-exclusive rights
to handle work at wreck sites are not relevant here. The decision to call
them out had been made in connection with the wreck and they performed work
on it. The question is whether or not carrier was justified in restricting
their work to the actual emergency then relieve them and complete the work
with an outside contractor. There is no explanation given by the carrier
to justify the relieving of the Sayre Wrecking Crew. For instance, a claim
that such crew was needed to handle another emergency situation could go
far to establish the reasonableness of the Carrier's actions here. Based
upon this record the Carrier, in effect, asserts a right to determine as a
matter of management prerogative the duration and scope of the work of the
wrecking crew after it is called.
The Carrier's own statement by its Director, Labor Relations and
Personnel, letter dated March 5, 1976, while the matter was on the property,
stated in part:
"... the rules only provide that when a wrecking crew is used
does the element of exclusive rights accrue to members of
the wrecking crew who are Carmen and are used to clear up a
wreck or derailment."
I
Form 1 Award No.
7523
Page
3
Docket No.
7403
2-CR-CM-'
78
The Carrier's argument to this Board confirms this:
"WHEN a wreck crew is called - then the work accrues
to Carmen." (emphasis theirs).
The only way we believe Carrier's position can be rationalized here
would b e to suggest there were two separate jobs: that on September 3 and
that on September
6, 1975.
But the facts are clear there was only one wreck.
Granted, the work on September 3rd involved the clearing of the mainline
and it was in the nature of an emergency. The work performed or, September
6th was not of an emergency nature. Then the mainline was cleared and only
rerailing cars and clean-up was required. Only if we so divide this work and
adopt Carrier's view that it can so make one job into two, or even three or
four can we reach this conclusion. We cannot do that and we rely upon the
reasoning advanced in Award
6845
(Twomey) in reaching this conclusion.
Carrier relies upon Award
6286
(McGovern) for its position. We do not
believe the facts are apposite and the rule relied upon is inapplicable.
There the wrecking crew was not used and the concept of "need" is used in
a different context as follows:
"Since the termination of the need for a wrecking crew
within the purview of Section (a) involves managerial
discretion and justment, we are of the opinion that
carrier's decision can successfully be challenged before
this Board only on the ground that it was arbitrary,
capricious, discriminatory or an abuse of managerial
discretion."
The managerial prerogative that Carrier seeks to assert here is far
too broad. When the Sayre crew was worked at the wreck site their rights
attached in accordance with Rule
125.
If the Carrier could then assert
rights of managerial prerogative to restrict or limit such rights or any
basis it sees fit, such as, restricting those rights to an emergency, the
wrecking crews' rights would be tenuous, indeed. We find no such authority
in the rule. It does not refer to emergencies and, in fact, it is broadly
worded to cover "wrecks or derailments". Clearly, the work performed by
the outside contractor resulted from the wreck and derailment and it would
be difficult to argue the Sayre crew had no rights to such work. We are not
disposed to define the precise nature of the work the Sayre crew could claim.
We take note, however, that clean-up work in connection with a wreck is
not excluded by the rule.
We do not suggest that the Carrier under no circumstances could
exercise such managerial prerogative to restrict the Sayre crews work at
this wreck site. We have already suggested one possible circumstance. We
do not rule out others. By analogy the "contracting out" cases are relevant.
See Award
2377.
The point we make is that Carrier must justify its actions
in situations as this. And such justification must be evaluated as to its
Form l Award No. 7523
Page 4 Docket No. 7403
2-CR-CM-'
78
reasonableness in determining whether or not Carrier acted arbitrarily,
'capriciously or discriminatorily. Absent such justification we have no basis
to deny the rights asserted by the Sayre Wrecking Crew as to the work
performed by the outside contractor. The record indicates the Sayre crew
was available to perform the disputed work.
We are persuaded that the awards cited by the Organization are pertinent
-here although none involve fact situations closely related to this case.
Awards 4581 (McDonald);
496-I-
(Johnson);
6030
(2umas); 6257 (Shapiro);
6490
(Bergman); 6847 (Twomey; and 7181 (Marx). In a somewhat different
context, and not an emergency, Referee Shapiro in Award 6257 made a
statement which reflects our reasoning here:
"When claimants charge that carrier's action was in
derogation of a specific contractually provided benefit
to which they believe they are entitled, it becomes
incumbent upon the carrier to offer a reasonable
explanation for its need to utilize other employes
and most particularly total strangers to the Railroad
in place of them. Its failure to do so brings it within
the limitations upon its use of its discretion and
judgment referred to hereinabove."
We are not aware of arty award of this Board, with one exception, that
follows a contrary position on facts such as those involved here. Award
5608 (Dorsey) involved distinguishable facts, in that it involved a different
carrier and different rules. However, that opinion appears to follow a
contrary view and in deference to the referee's distinguished record we
quote two paragraphs from that award:
"The theory argued by Petitioner in the instant case is
that when the Carrier has made a determination that a
wrecking crew is 'needed' all the work involved then
becomes exclusively reserved to Carmen and Carrier is
obligated to assign a sufficient
number
of Carmen to
the wrecking crew to perform all the work. We find no
support of the premise in 'pule 88(a) and (c). The only
qualification
of
carrier's inherent management
prerogative to determine the number of employes assigned
to a wrecking crew under arty circumstances is:
'a sufficient number of the
...
crew will accompany the outfit.'
Rule 88(a) and (c) does not mandate that a wrecking crew
shall. consist of sufficient Carmen to perform all the
work involved as a result of a wreck - the interpretation
which Petitioner seeks. It does not expressly reserve
to a wrecking crew, which the Carrier finds 'needed', the
I
Form 1
Page
5
Award No.
7523
Docket No.
7403
2-CR-CM-'78
"exclusive right to all the work in the wrecking
service. The words 'when needed' connote 'to the
extent needed,.,,
Referee Dorsey cites no authority fox this view. This Board has
uniformly held that it may not amend or add to ,rules. We rely
upon
the
numerous cases cited by the Carrier in this case to that effect. The
Supreme Court of the United States in West Coast Hotel Co. y. Parrish,
300 U.S. 379 , 401+ (1936)
said:
"The judicial function is that of interpretation;
it does not include the power of amendment under
the guise of interpretation."
It is sufficient to -point out that the word "needed" does not appear in
Rule
125.
The use of this phrase in Rule 124, however, is in a different
context, one not relevant here. The interpretation advanced in Award. 5608,
above, may be appropriate for that agreement but we do not believe it can
be extended to this. On this basis we believe such an interpretation here
would be outside the contemplation of the parties when they made this agreement and we are not inclined to follow it. The view we follow is consonant
with the plain wording of the rule.
In
our view of this case, we find no reason to consider the organization's
argument related to the matter of contract interpretation. As we see it,
the contractual requirements are clear under the applicable circumstances.
The record is not sufficiently clear on the damage question and we are
not authorized to award a penalty under this agreement. However, the
carrier has not raised an objection on that basis and insofar as the work
in question was performed three days later on a Saturday, at a time when
there was no emergency, we must assume the individual claimants who were
deprived of the work were entitled to be made whole by awarding them
compensatory damages in accordance with the claim, including travel
pay. Therefore, we find the contract was violated.
A W A R D
Claim sustained.
Attest: Executive Secretary
National Railroad Adjustment Board
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Second Division
Ro`s`erie Brasch - Adrniriistrative Assistant
Dated at Chicago, Illinois, this 25th day of April, 1978.