Form 1
Dispute: Claim of Employes:
NATIONAL RAILROAD ADJUSTMENT BOARD Award No,
7820
SECOND DIVISION Docket No.
779+-T
2
AT&SF-EW-'79
System Federation No.
97,
Railway Employes,
( Department, A. F. of L. - C. 1.0.
Parties to Dispute: ( (Electrical Workers)
(
( Atchison, Topeka and Santa Fe Railway Company
That the Carrier erred and violated the contractual rights of
R. E. McMahon and R. L, Bonham when they assigned Electricians work
to the Sheetmetal Workers.
(2) That, therefore, R. E. McMahon and R. L. Bonham be compensated
fox twelve (12) hours at their pro rata rate of pay.
Statement:
The above question was submitted to the Second Division of the National
Railxaod Adjustment Board by the above referred to organization in ex
paxte foam, hearing thereon was waived, and the Division is now in receipt
of a request from the employes that the case b e withdrawn.
A W A R D
Claim dismissed.
Attest: Executive Secretary
National Railroad Adjustment Board
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Second Division
Dated ai
emarie Brasch - Admi.nis xative Assistant
Chicago, Illinois, this 24th day of Januarys
1979·