Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No.
7829
SECOND DIVISION Docket No.
7+91
2-SCL-EW-'79
The Second Division consisted of the regular members and in
addition Referee Abraham Weiss when award was rendered.
( System Federation No.
42,
Railway Employes' _
( Department, A. F. of L. - C. I. 0.
Parties to Dispute: ( (Electrical Workers)
(
( Seaboard Coast Line Railroad Company
Dispute: Claim of Employes:
1. That the Seaboard Coast Line Railroad Company violated the
current working agreement, in particular the Letter Agreement
dated December
20, 1967,
when Carrier allowed subcontractor of
Queen City Constructors to work in excess of the Communications
Maintainers' normal work day on the dates of October 15, 16,
1'T, 21,
22, 23, 24, 25, 29, 30 & 31
and November 1,
4,
59
6~,
7, 8
and 11,
1974.
2. That, accordingly, the Carrier be ordered to additionall compensate
Communications Maintainer G. T. Langston twenty-seven (27) hours
at his punitive rate of pay.
Findings:
The Second Division of the Adjustment Board, upon the whole record and
all the evidence, finds that:
The carrier ox carriers and the employe or employes involved in this
dispute are respectively carrier and employe within the meaning of the
Railway Labor Act as approved June 21,
1934.
This Division of the Adjustment Board has jurisdiction over the dispute
involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
A Letter Agreement between the parties dated December 20,
1967
provides
that when work is contracted out:
"..,a telephone maintainer will be .present to lend assistance
to the contractor. In the event a telephone maintainer is
not available, and the contractor performs work in excess
of the maintainer's normal workday, penalty payment will
be made to the telephone maintainer for such excess hours
worked,"
Foam 1 Award
No.7829
Page
2
Docket No.
7491
2-scz-Ew-'79
Claimant, a communications maintainer, alleged that a subcontractor had.
worked
in
excess of his -work day on specified dates, starting October 15
and ending November 11,
1974,
and accordingly requested compensation at the
punitive rate of time and one-half for overtime worked by the contractor's
crew
on
such dates, in accordance with the Letter Agreement.
The issue in this case~is a relatively narrow one: Did the subcontractor
perform work in excess of the Claimant's work day on any of the dates
specified in the grievance and if so, what was the total number of such
excess hours worked? Claimant named
18
days on which the subcontractor
allegedly worked in excess of his normal work hours and thus claimed a
total of
27
hours. Carrier, on the other hand, contends that the subcontractor worked only one hour in excess of the Claimant's work day on each
of two days, and, therefore, offered to compensate Claimant for two hours
at the penalty rate of pay. Carrier's offer was rejected.
In support of his claim that the subcontractor had violated the
Letter Agreement., Claimant cited "outside sources" and filed a personal
notarized statement dated June 20,
1976,
submitted after his claim had been
declined by Carrier's highest officer of appeal. Claimant's June 20,
1976
affidavit states, in pertinent part:
"T was with contractor from November
5
through 12,
1974,
My hours were from
7:30
a.m. to
4:30
P.m. I came on
duty at Dillon, S.C.,, by the time I checked all circuits,
I arrived where contractor was working approximately
8:30
a.m. to
9
a.m., I remained with contractor until
3
_p.m. to
5:30
p.m. ~ leaving him working. In conversation
with Milam crew, I learned that they were working from
sunrise which was around
7
a.m, to dark which was around
5:45
p.m. each day, had been since returning to job. I
deceived this information from members of crew, Fritz Milam.,
brother of contractor, crew members Junior and Harold
(I do not remember their last names)."
Claimant submitted no substantive evidence from arty of the "outside sources"
to which he referred.
Claimantts own notarized statement, quoted above, indicates that he was
not at the site where the subcontractor was working on
9
of the
18
days fox
which claim was filed.
The record reveals that on 5 of the remaining days, Claimant arrived at the subcon·
tractor's work site after Claimant's
7:30
a.m. regular starting time
(8
a.m.
on one day, 8:15 a.m. on another day, and 9:00 a.m. on the other three
days). On these same
5
days, Claimant left the job site at
4:00
or
4:30
p.m. on one day; between 4:00 and
4:30
on another day; between
4:30
and
5:00 P.m. on two days; and at
5:30
P.m. on the fifth,day. On three of
Foam 1 Awaxd~No.
7829
Page
3
Docket No. 7+91
2-SCL-EW-`79
these days, Claimant states the subcontractor was still working when he
left. (On one of these days, Claimant left the job between x+:00 and x+:30
p.m.; on the other two, at 5:00 P.M.)
Carrier, in rejecting the claim, submitted a transcript of the hearing
hexeinabove referred to, the subcontractor's payroll records fox the dates
in question, and two affidavits by signal maintainers who denied that the
subcontractor worked overtime. One signal maintainer specifically stated
that the subcontractor's crew left fox work at the same time he did.
The subcontractor's payroll records show that one hoax overtime was
worked by the subcontractor's crew on two days (including November 12),
and Carrier offered to .pay the claim fox these two days, notwithstanding
that the claim as submitted was fox a period ending November 11. It was on
November 11 that Claimant left the job at 5:00 p.m. anal asserted that the
subcontractor was still working when he left.
We must conclude, on the record before us, that Petitioner has not
met the burden of proof. It is a
truism
that the burden of proof lies
upon the .party which asserts the affirmative of the issue. The burden
here is upon the Claimant, not the Carrier. Claimant submitted no
substantive evidence from any of the "outside sources" to Which he referred,
to confirm ox buttress his allegations. The evidence submitted by Claimant,
in the form of assertions not otherwise supported by probative evidence,
fails to make his case.
Claimant's own statements indicate that he was not present at the
subcontractor's job site at least half the days fox which he filed his
claim, and thus had no personal knowledge of the hoax°s during which the
subcontractor performed work. On several of the days when he woxl>ed with
the subcontractor, he either showed up after his normal 7:30 a.m. starting
time ox left before his normal 4:30 quitting time. The subcontractor's
payroll records fox the period in question must be given considerable weight
and accordingly, we conclude that Claimant is entitled, as Carrier offered.,
to two hours' compensation at time and one-half fox the excess hours worked
by the subcontractor on November 11 and 12.
A W A R D
Claim sustained to the extent indicated in the Findings.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Second Division
Attest: Executive Secxetary
National Railroad Adjustment Board
By 1
`-yes .,._..~·~ .~
~~.~=.'~,'.~°"'-,~
semarie F3xasch - Administrative Assistant
Dated~t Chicago, Illinois, this 7th day of February, 1979.