Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 7892
SECOND DIVISION Docket No. 7696-T
2-BNI-EW-'79





Parties to Dispute: '~"' (Electrical Workers)



Dispute: Claim of Employer:

















Findings:

The Second Division of the Adjustment Board, upon the whole record and all the evidence, finds that:

The carrier or carriers and the employe or employer involved in this dispute are respectively carrier and employe within the meaning of the Railway Labor Act as approved June 21, 193+.

This Division of the Adjustment Board has jurisdiction over the dispute involved herein.



An ice and snow storm on March 29 and 30, 1976 caused damage to Carrier's signal and communications wires over a 70-mile area. Carrier assigned both Communications and Signal Department employees to repair the damage. At issue is work performed on poles and pole lines.
Form 1 Award No. 7892
Page 2 Docket No. 76x6-T
2-BNI-EW-'79

Petitioner alleges that the Carrier assigned signal employees to perform work covered by the Electrician's agreement and, consequently, violated the Agreement, particularly Rule 26 of the general rules and Rules 46, 48(j) and x+8(1) of the Communication Agreement special rules. Petitioner's claim is that additional communications crews, including the claimants, should have been called to assist in the restoration of the pole lines in place of Signal Department crews.

Rule 26 (Assignment of Work) provides that "none but mechanics regularly employed shall do mechanics' work as per special rules of each department".

Rule 46 is a Scope Rule pertaining to employees of the Communications Department covering, among other functions, "the construction, repair and maintenance of telegraph and telephone pole lines, wires, cables, crossarms, braces, anchors, guys and appurtenances thereto, ...".

Rules 48(j) and X8(1) define the employment classifications of Crew Foreman Class 3 and Crew Lineman Class 5. The Crew Foreman is "assigned to supervise the construction and repair of pole lines and supports, ...". The Crew Lineman is "assigned to a crew to construct, maintain and repair pole line and supports, ...".

The Carrier argues that an emergency existed because of the storm and supplied supporting documentation of the extent and effect of the stom. The snow storm, it maintains, called for extraordinary action which warranted the use of all employees, including Signal Department employees, who were available and on the scene. It did, in fact, call in additional communications crews from other areas to supplement the communications crew assigned to the area in which the storm occurred.

In addition., Carrier states, the poles involved in the dispute carried both communications and signal lines and it was the practice tow ork communication and signal crews together in restoring pole lines damaged by storm or other causes creating an emergency. Further, it asserts, the repair of damaged pole lines carrying both lines was not work exclusively assigned to communications employees but was work that was assigned jointly to them and the signal employees.

The record indicates that Petitioner has failed to demonstrate that signalmen were assigned by the Carrier, as Petitioner claims, "to the repair of only Communication facilities, such as communication pole lines, wires, crossarms, braces, insulators, etc . ..."

As has been mentioned sllrra, the poles carry both signal and communica
tions lines. Rules 46 + l, and ) of the Electrical Workers' Agreement and
Rule 1 of the Signal-men's Agreement provide that both crafts perform repair
work on poles.
Foam 1 Award No. 7892
Page 3 Docket No. 7696-T
2-B1VI-EW- `79

An emergency created by the storm did exist. Carrier, accordingly, was confronted with the necessity to restore both communications and signal facilities in the shortest time possible. An emergency has been recognized by prior decisions of this Board as permitting a Carrier broader latitude than under normal circumstances to deploy its forces to meet the exigencies of the situation, subject to compliance to the relevant provisions of the applicable Agreement insofar as possible under the circumstances. Insofar as can be determined from the record, no showing has been made that in this cases Carrier abused such latitude.

During the period involved in repairing the poles and pole lines, the Carrier employed both Electrical Workers and Signalmen. It augmented the electricians' work force by bringing in communications employees (Electricians) from outside the storm area. Although the claimants may not have been called in for the emergency repair work, they were employed on their regular assignments during this period, as part of the process of maintaining the Carrier's operations outside the storm area.

The Fourth Division of this Board in Award No. 3599 (Marx, Jr.) recently denied a claim between the same parties on the same issue arising out of the same circumstances as in the instant case. The Board there stated:





We are in accord with the reasoning and conclusions of Award No. 3599 and are satisfied that the Award was proper. We will follow Award No. 3599 and, accordingly, will deny the claim.




Form 1 Award No. 7892,
page 4 Docket No. 7696-T
2-BNI-Ew- t 79
NATIONAL RAILROAD ADJUSTPvENT BOARD
By Order of Second Division

Attest: Executive Secretary
National Railroad Adjustment Board



By - ~sc~ ..
s rie Brasch - Administrative Assistant