Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No.
7892
SECOND DIVISION Docket No.
7696-T
2-BNI-EW-'79
The Second Di~r.si.Qr, consisted of the regular members and in
addition Ref~zw.; a:.s:z~.rla~ Weirs when award was rendered.
( System Federation No.
'T,
Railway Employer'
( Department, A, F. of L. - C. I. 0.
Parties to Dispute:
'~"'
(Electrical Workers)
( Burlington Northern Inc.
Dispute: Claim of Employer:
1. That in violation of the current agreement the Burlington Northern
Inc. assigned work which is under the jurisdiction of the
Communication Department. Employees to another department
namely the signal department, (sic)
2,
That accordingly the Burlington Northern Inc. be ordered to
compensate Communication Lineman - R. A. Nelson, R. R. Edwards,
R. E. Rusdal, E. A. Versland, G. D. Hennessy, J. E. Johnson,
R. R. Oss, J. E. Staffel, R. J. Bec1nan, U. W. Deniers, td. D.
Fauske, R. D. Peterson, E. J. Knapton, R. J. Fauske, L. R. Gilbert,
D. L. Erickson., R. A. Derhamel, J. A. Smith, D. L. Hulton and
D. Z. Rodenhizer, hereinafter referred to as the Claimants, in
an amount equal to the total nu.~nber of hours worked by the signal
employees. Claim to start April 1,
1976,
and to continue until
adjusted at the appropriate pro rata and punitive rates.
Findings:
The Second Division of the Adjustment Board, upon the whole record and
all the evidence, finds that:
The carrier or carriers and the employe or employer involved in this
dispute are respectively carrier and employe within the meaning of the
Railway Labor Act as approved June 21,
193+.
This Division of the Adjustment Board has jurisdiction over the dispute
involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
An ice and snow storm on March
29
and 30,
1976
caused damage to
Carrier's signal and communications wires over a 70-mile area. Carrier
assigned both Communications and Signal Department employees to repair
the damage. At issue is work performed on poles and pole lines.
Form 1 Award
No. 7892
Page 2 Docket
No. 76x6-T
2-BNI-EW-'79
Petitioner alleges that the Carrier assigned signal employees to
perform work covered by the Electrician's agreement and, consequently,
violated the Agreement, particularly Rule
26
of the general rules and Rules
46, 48(j)
and x+8(1) of the Communication Agreement special rules.
Petitioner's claim is that additional communications crews, including the
claimants, should have been called to assist in the restoration of the
pole lines in place of Signal Department crews.
Rule 26 (Assignment of Work) provides that "none but mechanics regularly
employed shall do mechanics' work as per special rules of each department".
Rule
46
is a Scope Rule pertaining to employees of the Communications
Department covering, among other functions, "the construction, repair and
maintenance of telegraph and telephone pole lines, wires, cables, crossarms,
braces, anchors, guys and appurtenances thereto,
...".
Rules
48(j)
and
X8(1)
define the employment classifications of Crew
Foreman Class
3
and Crew Lineman Class 5. The Crew Foreman is "assigned
to supervise the construction and repair of pole lines and supports,
...".
The Crew Lineman is "assigned to a crew to construct, maintain and repair
pole line and supports,
...".
The Carrier argues that an emergency existed because of the storm
and supplied supporting documentation of the extent and effect of the stom.
The snow storm, it maintains, called for extraordinary action which
warranted the use of all employees, including Signal Department employees,
who were available and on the scene. It did, in fact, call in additional
communications crews from other areas to supplement the communications crew
assigned to the area in which the storm occurred.
In addition., Carrier states, the poles involved in the dispute carried
both communications and signal lines and it was the practice tow ork
communication and signal crews together in restoring pole lines damaged by
storm or other causes creating an emergency. Further, it asserts, the repair
of damaged pole lines carrying both lines was not work exclusively assigned
to communications employees but was work that was assigned jointly to them
and the signal employees.
The record indicates that Petitioner has failed to demonstrate that
signalmen were assigned by the Carrier, as Petitioner claims, "to the
repair of only Communication facilities, such as communication pole lines,
wires, crossarms, braces, insulators, etc . ..."
As has been mentioned sllrra, the poles carry both signal and communica
tions lines. Rules
46 + l,
and ) of the Electrical Workers' Agreement and
Rule 1 of the Signal-men's Agreement provide that both crafts perform repair
work on poles.
Foam 1 Award No.
7892
Page
3
Docket No.
7696-T
2-B1VI-EW-
`79
An emergency created by the storm did exist. Carrier, accordingly,
was confronted with the necessity to restore both communications and signal
facilities in the shortest time possible. An emergency has been recognized
by prior decisions of this Board as permitting a Carrier broader latitude
than under normal circumstances to deploy its forces to meet the exigencies
of the situation, subject to compliance to the relevant provisions of the
applicable Agreement insofar as possible under the circumstances. Insofar
as can be determined from the record, no showing has been made that in this
cases Carrier abused such latitude.
During the period involved in repairing the poles and pole lines, the
Carrier employed both Electrical Workers and Signalmen. It augmented the
electricians' work force by bringing in communications employees (Electricians)
from outside the storm area. Although the claimants may not have been
called in for the emergency repair work, they were employed on their regular
assignments during this period, as part of the process of maintaining the
Carrier's operations outside the storm area.
The Fourth Division of this Board in Award No.
3599
(Marx, Jr.)
recently denied a claim between the same parties on the same issue arising
out of the same circumstances as in the instant case. The Board there
stated:
",., no showing was made of any rule violation when
the Carrier utilized employees of the two crafts on
poles and lines where work of the two crafts is
commingled. Nor is it demonstrated that the
Carrier is required to have two separate crafts
work together in each work situation under the
existing circumstances.
In reaching this conclusion, the Board confines
its ruling to this particular dispute. Use of
Electrical Workers and Signalmen was designed
to deal with the emergency situation, involving
severe time constraints. At the wane time
the organization has failed to show that others
performed work which belonged exclusively to its
members. "
We are in accord with the reasoning and conclusions of Award No.
3599
and are satisfied that the Award was proper. We will follow Award No.
3599
and, accordingly, will deny the claim.
A W A R D
Claim denied.
Form 1 Award No. 7892,
page
4
Docket No. 7696-T
2-BNI-Ew-
t
79
NATIONAL RAILROAD ADJUSTPvENT BOARD
By Order of Second Division
Attest: Executive Secretary
National Railroad Adjustment Board
.~-.cc`- '
By - ~sc~
..
s rie Brasch - Administrative Assistant
Dated at Chicago, Illinois, this 19th day of April, 1979.