Form 1 NATIONAL RAILROAD ADJUSTMETTr BOARD Award No. 7960
SECOND DIVISION Docket No. 7808
2-CMStP&P-CPI-' 79





Parties to Dispute: ( (Carmen)
.._.. (



Dispute: Claim of i'71:mloyes:





Findings:

The Second Division of the Adjustment Board, upon the whole record and all the evidence, finds that:

The carrier or carriers arid the ozn.ploye or employes involved in this dispute are respectively carrier and employe within the meaning of the Railway Labor Act as approved June 21, 19316.

This Division of the Adjustment Board has jurisdiction over the dispute involved herein.



Petitioner alleges that the Carrier used an outside contractor to dismantle freight cars for scrap, following a derailment at Canton, S.D.., although such work had been previously performed by Carmen on a m:Tstem-pride basis. Petitioner, accordingly, claims a violation of Rules 85 (Carmen's Classification of Work Rule); 31(a) (Seniority); 32(a) (Assignment of Vox:11); and 33 (Assignment of Welding Work).

Carrier, on the other hand., refers to its lord-standing practice to contract out work such as that involved in the instant claim; that in a pr:i.or situation, it had agreed with the Organization that "the salvaging of usable parts a t a derailment would be perior7ned air the Carmen Craft"; that the current claim did not involve a salvage operation but a scrap operation, in that the contractor tress used "to cut up and load the destroyed freight
Foam 1 Page 2

Award No. 7960
Docket No. 7808
2-ChZStP° P-CM-' 7H

cars ... for shipment to St. Paul Store Department for disposition and sale of the scrap"; and that the cuttin~ up of scrap car is not encompassed in the Caxnnen's Classification of Work Rule nor is such work reserved exclusively to Carmen.

Both parties in their Submissions arid during the processing of the claim on the property referred to a prior case -- the Nina case. Carrier's position is that in the I%1ina case it used a contractor to salvage usable parts, which it acknowledged was C armen's work. However, the cutting up of the cars for scrams loading, also perfo?~:ed by the contractor, was not considered Carmen 's i-,ork and no claim was made for that work in the handling of that case.

The instant case is distinguishable, according to Carrier, in that Carmen (not the contractor) sa1Z~a..ed the usable parts, Unlike the Mina case, therefore, the instant claim involves only the cutting up of cars for scrap. And on that issue, Carrr_er submitted a list showing, over a 5-year period, that it had used contractors for cutting up for scrap, cars involved in derailments.

In swn, on the basis of the disposition of the Mina case and the Carmen's Work Classification Rule, Carrier denies that the work in question is reserved to Caxznen.


work eras not a salvage operation but a scrap process, and that the contractor
was used. only after members of the Carmen craft had cum- - leted the salvaging
of parts operation. Tao probative evidence has been submitted by Petitioner
that the contractor used by the Carrier performed salvage work or that cutting
up of scrap is either contractually reserved to Carmen or that such work
belongs to Carmen on the basis of past practice. Carrier's records and
itemization of use of contractors over a 5-year period. effectively refutes
Petitioner's allegations. Accordingly, we wild. deny the claim.

A W A R D

Claim denied.

Attest: Executive Secretary
National Railroad Adjustment Board

NATIOTafL RAILROAD ADdUSTAEIV'I' BOARD

By Order of Second Division




Dated at Chicago, Il:l:inois, this 13th day of dune, 1979.