Form 1 NATIONAL RATLROAD ADJUSTMENT BOARD Award No. 8158
SECOND DIVISION Docket No. 7551
2-WP-CM-'79





Parties to Dispute: ( (Carmen)




Dispute: Claim of Employes:





Findings:

The Second Division of the Adjustment Board, upon the whole record and all the evidence, finds that:

The carrier or carriers and the employe or employes involved in this dispute are respectively carrier and employe within the meaning of the Railway Labor Act as approved June 21, 1934.

This Division of the Adjustment Board has jurisdiction over the dispute involved herein.



On April 77.., 1976, one of Carrier's locomotives was derailed at Marblehead, Utah, blocking the main line. Carrier called out its wrecking crew from Elko, Nevada, with its derrick to rerail the engine. The Elko derrick and crew were unable to rerail the engine because the derailed Yrheels were on the east end of the unit and the Elko Derrick had no way to get around the derailed unit to its east end where it could reach the derailed wheels. Consequently, Carrier requested the D&RGW RR to send its derrick from Salt Lake City to rerail the Engine. The D&RGW Derrick and crew was called at 5:00 A.M. on April 11th and the work was completed at x+:00 P.m. that afternoon. The Elko Derrick and crew had been released and did not participate in the rerailing.

The organization relies on the December 4, 1975 Agreement and in particular Article VII, which provides:
Form 1 Award No. 8158
Page 2 Docket No. 7551
2-WP-CM-'79





















Carrier contends that the first phrase of Article VII must be construed to qualify the applicability of the language; in this case Rule 115 of the Agreement must be also considered. That language provides:



Carrier's principle argument was that the provisions of the National Agreement were not applicable to using equipment of another railroad, but applied only to outside contractors - outside of the industry. In this case, Carrier argues, the work in question was not performed by outside contractors but by Carmen covered by the same National Agreement, even though employed by a different Carrier. Further, Carrier urges, it had no right to require or assign its employees to the use of D&RGGT equipment. On the other hand, Petitioner cites several awards of SBA 570 (Awards 61 and 62). The Organization claims that Carrier should have called its crew, under the Natiomi1 Agreement, with the contractor's (in this instance the D&RGW) outfit.

Unfortunately, the intent of the parties in the drafting of Article VII is not at all clear from the record of this dispute. However, certain previously enunciated principles of this Board are relevant in the disposition of this dispute. First, it is well established that when a derailment occurs outside of yard limits, as herein, (under~the provisions of Rules such as 115 supra) and the services of a wrecker are not required, the wrecking crew does not have exclusive right to perform that work (see Awards 7526, 7074 and 7670 among many others). In Award 7744, we dealt with a closely related issue and held that there is no conflict between Article VII and rules such as 115. In that Award, we said:
Form 1 Page 3

Award No. 8158
Docket No. 7551
2-WP-CM-'79

"The former (referring to Article VII) memorializes the Carrier's right to use outside wrecking services while requiring the use of wrecking crew members as specified but 'pursuant to rules or practices'. Rule 120 is not superceded by Article VII, Section 1. To accept the organization's position would be to give a new interpretation to Rule 120, Since the parties have not disturbed Rule 720, the Board has no reason to change its interpretation of such rule,"

It also must b e noted, on a factual basis, that the members of the Elko Wrecking Crew were located 205 miles from the site of the wreck and hence Carrier found that they were not "reasonably accessible".

Based on the reasoning expressed in Award 7744, we find that the provisions of Rule 115 must still. be considered in this dispute and that the work in question was not exclusively reserved to Claimants herein. That fact plus the relative inaccessibility of the Elko Crew persuade us that the Claim does not have merit. It must be made clear, however, that we are making no judgment with respect to whether carmen from another Carrier must be considered to be in the same posture as employes of an outside contractor.

A W A R D

Claim denied.

Attest: Executive Secretary
National Railroad Adjustment Board

NATIONAL RAILROAD ADJUSTl'.ENT BOARD

By Order of Second Division


$ semarie Brasch - Administrative Assistant

Dated t Chicago, Illinois, this 14th day of November, 1979.