Form 1
Parties to Dispute:
Dispute:
Claim of Employes:
NATIONAL RAILROAD ADJUSTMENT BOARD Award No.
8235
SECOND DIVISION Docket No.
8091
2-S00-CM-'$0
The Second Division consisted of the regzlar members and in
addition Referee George S. Roukis when award was rendered.
System Federation No.
7,
Railway Employes'
Department, A. F. of L. - C. I. 0.
(Carmen)
( Soo Line Railroad Company
1. The Soo Line R. R. violated Rules
28, 94, 97
and
98
of controlling
agreement when on March
28
and March
29, 1977
they secured the services
of an outside contractor consisting of two (2) operators and equipment
from Avon, Minnesota to rerail cars due to deraiL.ent of train -,;o. 9'+;2
on a siding at Paynesville, Minnesota on March 25,
1977.
2. That accordingly the Soo Line R.R. Co. be ordered to compensate the
Shoreham Shops, Minnesota Wrecking Crew members, namely:
Carmen
William Vados
David Terry
Ray Korzenowski
Allen Wilnot
William Fish
Douglas Granville
Delmar Parvey
Wrecking Engineer
Wrecking Engineer
Ground Crew
Ground Crew
Ground Crew
Ground Crew
Cook
in the amount of sixteen (16) hours at the Carmens time and one half rate
of pay each.
Findings:
The Second. Division of the Adjustment Board, upon the whole record and all.
the evidence, finds that:
The carrier or carriers and the employe or employes involved in this
dispute are respectively carrier and employe within the meaning of the Railway
Labor Act as approved June 21,
1934.
This Division of the Adjustment Board has jurisdiction over the dispute
involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
The threshold question raised in this dispute is whether or not the precise
conditions surrounding the derailment at Paynesville, Minnesota on March 25,
1977
and immediately thereafter posed an indisputable emergency that warranted the use of
an outside contractor.
Form 1 Award No.
8235
Page 2 - Docket No.
8091
2-soo-CM
1
So
Claimants argue that Carrier violated Agreement Rules
28, 94, 97,
and
98
respectively when outside forces were retained to perform this work, while Carrier
contends that the nature and the extent of the derailment coupled with the
impracticallity of rebuilding the track before being able to position Carrier
equipment at the derailment site justified its action. .
Our review of the record, particularly the data depicting the magnitude of
the derailment, does not support petitioners assertion that it was feasible to use
the Shoreham wrecker. On the contrary, we find that given the unmistakable eme^gency
that existed and Carrier's non ownership of mobile equipment, that Carrier acted
responsibly and consistent with its managerial prerogatives as defined in our
predecesser A,cardso (See, for example, Second Division Awards
4190, 6177, 6602,
6757
and
7979.)
In Award
7979,
which is on all fours with this dispute and involving the same
parties and the same type of issue, we held that Carrier's determination to use an
outside contractor was plainly permissible under the circumstances and denied the
claim. We find this ruling directly applicable to the fact specifics herein and
thus we are compelled to deny this claim. An emergency was present that required
Carrier to use an outside contractor to clear and revitalize promptly the deraiax:ent
site and it was neither a contract violation nor an abuse of managerial discretion.
A W A R D
Claim denied.
NATIONAL RAILROAD ADJUSTi1ENT BOARD
By Order of Second Division
Attest: Executive Secretary
National Railroad Adjustment Board
0
By
l- '--sir,.-~:c:
semarie Brasch - Administrative Assistant
Datedlat Chicago, Illinois, this 16th day of January
1980.