Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No.
8254
SECOND DIVISION Docket No.
8218
2-MP-EW-'80
The Second Division consisted of the regular members and in
addition Referee Herbert L. Marx, Jr. when award was rendered.
( System Federation No.
2,
Railway Employes'
( DepartmentDepartment, A. F. of L. - C. 1. 0.
Parties to Dispute: ( (Electrical Workers)
Missouri Pacific Railroad Company
Dispute: Claim of Employes:
1. That the Missouri Pacific Railroad Company violated Rules 1 and
24
of
the Corinunications Agreement effective August 1,
1977
and Article III
of the September
25, 1964
Agreement at St. Louis, Missouri when on
Wednesday, March 1,
1978,
from
9:40
a.m. to 1:30 p.m., Assistant
Project Manager Wilcox assigned himself to perform
Communications
Maintainers' work, i.e.., disconnecting Carrier and Bell Telephone modem
quad cables from a demark block (terminal block) then cutting and
splicing said cables, thereby depriving Communications Maintainer A.
Tate the provisions of the Agreements.
2.
That, accordingly, Carrier be ordered to compensate Communications
Maintainer A. Tate for Wednesday, March 1,
1978,
four hours
(4')
at
the time and one-half rate.
Findings:
The Second Division of the Adjustment Board, upon the whole record and all.
the evidence, finds that:
The carrier or carriers and the employe or employes involved in this dispute
are respectively carrier and employe within the meaning of the Railway Labor Act
as approved June 21,
1934.
This Division of the Adjustment Board has jurisdiction over the dispute
involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
In this dispute, there is little conflict as to the basic facts involved.
Carrier's Assistant Project Manager, a supervisory employe not covered under the
agreement applicable here, undertook to make certain alterations in wire and
cable connections required as part of video display terminals in the Carrier's
training room. The nature of the work is clearly covered under Rule 1, Scope,
of the applicable agreement, in which duties of Con~,,,.nznications Department
employes are defined. Claimant is a Comxmunications Maintainer, compensated on a
monthly basis and on his rest day (seventh day of week) on the date in question.
According to the Carrier, the Assistant Project Manager noted what he considered
to be hazardous electrical conditions, owing to the relocation of some of the
equipment in the training room. He first attempted to obtain the services of a
Communications Yaintainer on duty but was unsuccessful. He then proceeded to do
the work himself. There is some dispute as to the extent and purpose of this work,
but none that it was of a nature regularly assigned to Communications Maintainers.
Form 1
Page 2
Award No. 8254
Docket No. 8218
2-MP-EW-180
The Carrier defends its actions on the grounds that the Assistant Project
Manager was faced with an "emergency" owing to the hazardous conditions (exposed
wiring and equipment, etc.). The Organization strenuously denies that a genuine
't
emergency" existed.
Directly applicable is Article III of the September 25, 1964-Agreement which
reads in part as follows
"ARTICLE III - ASSIGT~24iENT OF WORK - USE OF SUPERVISORS
None but mechanics or apprentices regularly employed as such
shall do mechanics' work as per the special rules of,each craft
except foremen at points where no mechanics are employed."
In work jurisdiction disputes, the Organization bears the burden of proof
to establish its claim to the type of work involved; in this case, there is no
dispute on this point. Where the Carrier seeks an exception, for example the presence
of an emergency requiring action by a supervisor, it is the Carrier which must
offer substantial proof of its position. A thorough examination of the record
herein fair to show that an "emergency" existed requiring the supervisor to make
the wiring adjustments or that, if hazard did indeed exist, it could not have
been avoided in other ways.
The Carrier takes the position that, even if the claim is sustained, no
monetary remedy is required, owing to the nature of the Claimant's status as a
monthly-rated employe. The work involved here, however, was performed on the
Claimant's rest day, and he would have received extra compensation had he been
assigned the work. The monetary claim is thus in order but, in keeping with
established precedent, it is not payable at the punitive rate since the Claimant
was not actually called upon to perform the work.
A W A R D
Claim sustained at the straight time rate of pay.
NATIONAL RAILROAD ADJUSTTM7iTT BOARD
By Order of Second Division
Attest: Executive Secretary
National Railroad Adjustment Board
,~' Rosemarie Brasch - Adini nistrative Assistant
Dated 'at Chicago, Illinois, this 20th day of February, 1980.