Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 8295
SECOND DIVISION Docket No. 8233
2-EJ&E-CM- `80





Parties to Dispute: ~ (Carmen)




Dispute: Claim of Employes:





Findings:

The Second Division of the Adjustment Board, upon the whole record and a1.7. the evidence, finds that:

The carrier or carriers and the employe or employes involved in this dispute are respectively carrier and employe within the meaning of the Railway Labor Act as approved June 21, 193+.

This Division of the Adjustment Board has jurisdiction over the dispute involved herein.



An accident occurred on February 15, 1978 at the Commonwealth Edison Company plant in Waukegan., Illinois involving the derailment of car WP 35891 and the derailment and overturning of car L & N 111163. Carrier's Wreck Truck No. 157 was called to retail WP 35891· The Wreck Truck and its crew were not capable of uprighting and retailing L & N 71.163, and the crew was ordered to return to its previously assigned work. To perform the work, the services of the wreck truck of another Carrier, with supervisor and three-man crew were called in to perfoi:ln the work.
Form 1 Award No, 8295
Page 2 Docket No. 8233
2-EJ&E-CM-' 80

The organization claims that, under Rule 50, the eight-man crew of Wrecking Derrick #5 should receive eight hours' pay plus seven hovers' travel time at the punitive rate for each member of the crew.























The Carrier cites numerous previous awards denying pay to Carmen for wrecking services under a variety of circumstances, Without finding fault with the reasoning in such awards, the Board nevertheless finds that the particular circumstances here involved require the application of Rule 50 (c), in that the Carrier utilized the "equipment of a contractor ,,, for the performance of wrecking service..." Under the circumstances, where Carrier's wreck truck had already been involved in a portion of the work at the location in question, the claim for pay of Rule 50 (c) is sustainable, inclusive of applicable travel time as referred to in Rule 50 (a),
Form 1 Award No. 8295
Page 3 Docket No. 8233
2-EJ&E-CM-' 80

The Organization's claim is excessive, however, in calling for pay for an eight-man derrick crew, since no showing was made that such equipment or number of employes would be required if the Carrier itself had undertaken the work. Further, there is no dispute that the contractor who performed the work did so with a three-man crew, charging the Carrier for 28 hours of work.

The claim will therefore be sustained to the extent of payment of a total of 28 hours to be divided among three employee, plus three hours' travel time for each of the three employees determined judgmentally based on the distance displayed in the record. As in other instances involving pay for work not actually performed., all pay shall be at straight-time rate. The parties shall meet to determine which three employee shall be paid.



    Claim sustained to the extent provided in the Findings.


                            NATIONAL RAILROAD ADJUSTMENT BOARD

                            By Order of Second Division


Attest: Executive Secretary
National Railroad Adjustment Board

B y ~ff~semarie Brasch - Administrative Assistant

Dated alt Chicago, Illinois, this 26th day of March, 1g80.