Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No.
8472
SECOND DIVISION Docket No.
8250-T
2-HB8C-EW-' 80
The Second Division consisted of the regular members and in
addition Referee Rodney E. Dennis when award was rendered.
( International Brotherhood of Electrical Workers
(
Parties to Dispute:
(
( Houston Belt and Terminal Railway Company
Dispute: Claim of Employes:
1. That the Houston Belt and Terminal Railway Company violated Rules 22 (a)
and (b), 23, 100, and 102 of the September 1,
1949
controlling agreement
when they assigned Machinists E. E. William- to perform electricians'
work on Friday, June
9, 1978,
thus, depriving Electrician R. E. Netrow
his contractual rights under the provisions of the Agreement at Houston,
Texas.
2.
That, accordingly, Carrier be ordered to compensate Electrician R. E.
Netrow two hours and forth minutes
(2'40")
at the overtime rate for
Friday, June
9, 1978.
3.
In addition to the money amounts claimed herein, the Carrier shall pay
claimant an additional amount of
6%
per annum, compounded annually on
the anniversary date of the claim.
Findings
The Second Division of the Adjustment Board, upon the whole record and all.
the evidence, finds that:
The carrier or carriers and the employe or employes involved in this dispute
are respectively carrier and employe within the meaning of the Railway Labor Act
as approved June
21, 1934.
This Division of the Adjustment Board has jurisdiction aver the dispute
involved herein.
Parties to said dispute waived right of appearance at hearing thereon.
The Organization contends that carrier violated the agreement when it assigned
a machinist to 'operate the overhead crane in carrier's Diesel Shop at Houston,
Texas, on Friday afternoon, June
9, 1978.
The organization claims a call (two
hours and forty minutes at the overtime rate) for Electrician R. E. Netrow,
claimant in this case.
Carrier states that on June
9, 1978,
it found itself in a position wherein
it needed to use the overhead crane to finish the job of changing out a number one
traction motor on engine
54.
Since there was not an available electrician to
operate the crane, a machinist was assigned the task. He ran the crane, completed
the job, and engine
54
was put in service for the middle track on that date.
Carrier claims that it knew it needed an electrician to operate the crane on
Form 1 Award No.
8472
Page
2
Docket No.
8250-T
2 -Hs&T-EW-'
80
June
9, 1978
because the regular electrician assigned to the day shift, Leo
Wilson, could not climb into the crane, account he had a bad knee. In
anticipation of the need to use the crane to change the traction motor, carrier
called Electrician Wooldridge to come in. He could not accept the call, account
illness. It then contacted Electrician Netrow. Netrow would not accept the call,
account it was his day off. Carrier thereupon held over Electrician C. R. Wilson,
the 11:00 p.m. to
7:00
a.m. man, on the day shift to operate the crane.
At about 12:30 P.m., C. R. Wilson was called home on an emergency, account
his child was sick. This left the day shift without an electrician to run the
crane from 12:30 P.m. to 3:00 P.m. Carrier needed to complete the job of changing
the traction motor. It needed the crane to remove the jacks and allow the engine
to go back to service. It had made every effort possible to obtain an electrician
to do the work. No electrician was available. It assigned a machinist to do the
job. Carrier argued in its submission to this Board that it authorized this
work under the incidental work rule.
The organization denies that carrier called either Wooldridge or Netrow tc
come into work on June
9, 1978.
It also asserts that carrier did not advance the
incidental work rule argument on the property. Thus, it is barred from doing so
at this time.
The board is presented with a number of conflicting statements. While we
have repeatedly stated that we do not make credibility judgments, it is impossible
to arrive at a decision in this case if one party's story is not accepted as
being more logical and reasonable than the other.
After a thorough review and discussion of the case, this board is of the
opinion that carrier made a more than reasonable effort to have an electrician
available to operate the crane, but to no avail. Electricians at the location
were just not available and the one who was on duty could not perform the required
task. Given these facts, carrier should not be required to shut down its operation,
waiting for an electrician to come to work, or to pay a penalty because it relied
on someone other than an electrician to do the work.
This is not to say, however, that this board in any way has moved away from
its decision in Award
8078
and Public Law Board No.
1476.
The facts in this
case are in almost direct opposition to the facts present when Award
8078 was
rendered.
The board also states that the incidental work rule argument was not properly
before it and it has not been considered in this decision.
A W A R D
Claim denied.
Form 1
Page
3
Attest: Executive Secretary
National Railroad Adjustment Board
Award No. 8472
Docket No. 8250-T
2-HB8T-EW-' 80
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Second Division
By
marie Brasch - Administrative Assistant
Dated
s4
,Chicago, Illinois, this 22nd day of October,1980.