Form 1 NATIONAL RAILROAD ADJUSTMENT BOARD Award No. 8506
SECOND DIVISION Docket No. 8475
2-MP-EW-'80


Parties to Dispute:


Dispute: Claim of Employes:

1. That the Missouri Pacific Railroad Company violated Rules 3, 4-Section
1 (a), 5 (a), 6 (a), 7 (a), (d) and (g) of the Communications Agreement
effective August 1, 1977 when they denied Communications Maintainer
J. E. Brown at North Little Rock, Arkansas the overtime provisions of the
Agreement, i.e., two and seven-tenths hours (2.7') at the overtime
rate for work performed outside his bulletined hours - 10:00 P.M.
until 11:59 P.m. July 13, 1978.
2. That, accordingly, the Missouri Pacific Railroad Company be ordered to
compensate Copmiunications Maintainer J. E. Brown two and seven-tenths
hours (2.7') at the overtime rate for ~'uly 1.3, 1978.
Statement:

The above question was submitted to the Second Divisicn of the National Railroad Adjustment Board by the above referred to organization in ex parte form, hearing thereon was waived, and the Division is now in receipt of a request from the employes that the case be withdrawn.

                          A W A R D


      Claim dismissed.


                              NATIOVJL RAILROAD ADJUSUENT BOARD

                              By Order of Second Division


Attest: Executive Secretary
National Railroad Adjustment Board

          R

By 'r,
      osemarie Brasch - AdmLnistrative Assistant

41-00,

Datelat Chicago, Illinois, this 19th day of November, 1980.